5429 S MCCONNELL AVE 90066

Certificate Information: 5429 S MCCONNELL AVE 90066

Application / Permit
25016-10000-17965
Plan Check / Job No.
B25LA23116
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(22) Warehouse
Work Description
**ePlan**LAX** Exterior alteration at an existing commercial building property. Scope of work includes construction of a new exterior loading dock platform and corresponding ramp, along with the installation of new safety railings.
Permit Issued
Issued on 9/27/2025
Issuing Office
Current Status
Permit Finaled on 2/25/2026

Permit Application Status History

Submitted 6/4/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 FARSHAD ALIMOHAMADI
Corrections Issued 6/21/2025 FARSHAD ALIMOHAMADI
Quality Review Completed 6/30/2025 LIPING TENG
Applicant returned to address corrections 7/22/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 7/25/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 9/8/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 9/17/2025 FARSHAD ALIMOHAMADI
Issued 9/27/2025 APPLICANT
Permit Finaled 2/24/2026 DERRICK SPENCER

Permit Application Clearance Information

DAS Clearance Cleared 9/9/2025 Lily Teng

Contact Information

Architect Fisher,, Courtney Lynn; Lic. No.: C40320 2529 N 86TH ST      SCOTTSDALE, AZ 85257
Contractor T G Construction Inc; Lic. No.: 528058-B       ,
Engineer Herd,, Sandra Jean; Lic. No.: S4080 1215 W RIO SALADO PKWY STE 200      TEMPE, AZ 85281

Inspector Information

DANIEL ARMENTA, (310) 914-3925 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2025 Not Ready for Inspection NICK LAROCCA
Pre-Inspection 12/12/2025 Approved NICK LAROCCA
Deputy Drilled-In Anchors 12/15/2025 Partial Approval VASIL MIHALEV
Deputy Reinf. Concrete 12/15/2025 Partial Approval VASIL MIHALEV
Deputy Drilled-In Anchors 12/16/2025 Approved VASIL MIHALEV
Deputy Reinf. Concrete 12/16/2025 Partial Approval VASIL MIHALEV
Footing/Foundation/Slab 12/16/2025 Approved VASIL MIHALEV
Pre-Inspection 12/16/2025 Corrections Issued VASIL MIHALEV
Footing/Foundation/Slab 12/19/2025 Not Ready for Inspection VASIL MIHALEV
Reinforced Concrete Frame 12/19/2025 Not Ready for Inspection VASIL MIHALEV
Footing/Foundation/Slab 12/22/2025 Approved VASIL MIHALEV
Deputy Reinf. Concrete 12/23/2025 Approved VASIL MIHALEV
Footing/Foundation/Slab 12/23/2025 Approved VASIL MIHALEV
Notice of Violation 12/23/2025 Not Required VASIL MIHALEV
Deputy Reinf. Concrete 12/29/2025 Conditional Approval GRANT WOODS
Deputy Reinf. Concrete 2/6/2026 Approved DERRICK SPENCER
Excavation/Setback/Form/Re-Bar 2/6/2026 Approved DERRICK SPENCER
Deputy Reinf. Concrete 2/10/2026 Conditional Approval DANIEL ARMENTA
Final 2/24/2026 Permit Finaled DERRICK SPENCER
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved DERRICK SPENCER
Smoke Detectors 2/24/2026 Approved DERRICK SPENCER