3746 S REDWOOD AVE 90066

Certificate Information: 3746 S REDWOOD AVE 90066

Application / Permit
25016-10000-17946
Plan Check / Job No.
B25LA23096
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT EXISTING DETACHED GARAGE AND STORAGE INTO ADU PER LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 10/28/2025
Issuing Office
Current Status
Issued on 10/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/3/2025 APPLICANT
Assigned to Plan Check Engineer 6/6/2025 ALEC MOUSAKHANIAN
Corrections Issued 6/7/2025 ALEC MOUSAKHANIAN
Plan Check Approved 7/23/2025 ALEC MOUSAKHANIAN
Issued 10/28/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/16/2025 KIMBERLY HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 6/16/2025 KIMBERLY HERNANDEZ
Roof/Waste drainage to street Cleared 6/16/2025 KIMBERLY HERNANDEZ
Sewer availability Cleared 6/16/2025 KIMBERLY HERNANDEZ
Specific Plan Cleared 6/18/2025 RICHARD WOO
Construction near power lines Cleared 7/21/2025 RIDWAN HARDY
Construction within easement Cleared 7/21/2025 RIDWAN HARDY

Contact Information

Contractor Smart Eye Construction Corp; Lic. No.: 1077004-B       ,
Engineer Adzhemyan,, Arsen; Lic. No.: C89103 1010 RALEIGH ST APT 107      GLENDALE, CA 91205

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/30/2025 Partial Inspection WILBER ROSALES
Underground Mechanical 11/6/2025 Not Ready for Inspection WILBER ROSALES
Deputy Drilled-In Anchors 11/13/2025 Conditional Approval WILBER ROSALES
Excavation/Setback/Form/Re-Bar 11/13/2025 Approved WILBER ROSALES
Footing/Foundation/Slab 11/13/2025 Approved WILBER ROSALES
Underground Mechanical 11/13/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 2/25/2026 Partial Approval DAKOTA LOW
PLUMBING-Rough 2/25/2026 Corrections Issued DAKOTA LOW
ELECTRICAL-Rough 4/22/2026 Corrections Issued DAKOTA LOW
HVAC-Rough 4/22/2026 Approved DAKOTA LOW
PLUMBING-Rough 4/22/2026 Approved DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 4/30/2026 Approved RUBEN RIVAS
BUILDING-Rough-Frame 5/8/2026 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 5/8/2026 Approved RUBEN RIVAS
Green Building Rough 5/8/2026 Approved RUBEN RIVAS
Interior/Exterior Lathing 5/8/2026 Corrections Issued RUBEN RIVAS
BUILDING-Rough-Frame 5/14/2026 Approved DAKOTA LOW
Green Building Rough 5/14/2026 Approved DAKOTA LOW
Interior/Exterior Lathing 5/14/2026 Partial Approval DAKOTA LOW
Insulation 5/26/2026 Approved EVAN COOPER
Drywall Nailing 6/17/2026 Corrections Issued DAKOTA LOW
Interior/Exterior Lathing 6/17/2026 Approved DAKOTA LOW
Shower Pan 6/17/2026 Approved DAKOTA LOW