- Eplan CONVERT (E) DETACHED GARAGE TO ADU PER GC 66323(a)(4) CONSTRUCTION PER WFPP 2 OF 2
- Permit Issued
- Issued on 8/24/2025
- Issuing Office
- Current Status
- CofO Issued on 6/27/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | JOSEPH RAFOLS |
| Corrections Issued | 6/4/2025 | JOSEPH RAFOLS |
| Quality Review Completed | 6/12/2025 | SINA KHOSRAVI |
| Applicant returned to address corrections | 8/7/2025 | JOSEPH RAFOLS |
| Plan Check Approved | 8/21/2025 | JOSEPH RAFOLS |
| Issued | 8/24/2025 | APPLICANT |
| CofO in Progress | 6/22/2026 | BRIAN SULLIVAN |
| Permit Finaled | 6/27/2026 | DEROLD HAUFF |
| CofO Issued | 6/27/2026 | DEROLD HAUFF |
| Permit Finaled | 6/27/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2025 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2025 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 6/25/2025 | CINDY QI |
| Sewer availability | Cleared | 6/25/2025 | CINDY QI |
| Construction near power lines | Cleared | 8/13/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/30/2025 | Partial Approval | CRAIG VAUGHAN |
| Sewer | 10/1/2025 | Approved | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/8/2025 | Conditional Approval | BRIAN SULLIVAN |
| Excavation/Setback/Form/Re-Bar | 10/9/2025 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 10/9/2025 | Partial Approval | CRAIG VAUGHAN |
| Deputy Drilled-In Anchors | 10/20/2025 | Approved | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2025 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/24/2025 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/24/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/24/2025 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/1/2025 | Partial Approval | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 12/1/2025 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 12/1/2025 | Partial Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2025 | Approved | CRAIG VAUGHAN |
| Insulation | 12/4/2025 | Approved | CRAIG VAUGHAN |
| Shower Pan | 12/4/2025 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 12/9/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 12/16/2025 | Approved | ROY SPAULDING |
| Underground Mechanical | 2/26/2026 | Partial Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 4/10/2026 | Approved | CRAIG VAUGHAN |
| Final | 4/10/2026 | Partial Inspection | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/10/2026 | SGSOV Not Required | CRAIG VAUGHAN |
| Smoke Detectors | 4/10/2026 | Approved | CRAIG VAUGHAN |
| Final | 4/20/2026 | Partial Inspection | CRAIG VAUGHAN |
| Final | 6/22/2026 | OK to Issue CofO | BRIAN SULLIVAN |