200 WORLD WAY 90045

Certificate Information: 200 WORLD WAY 90045

Application / Permit
25016-10000-17795
Plan Check / Job No.
B25LA22870
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(3) Airport Building
Work Description
**ePlan**LAX** Tenant Imrovement work for 1- RECLASSIFY AND REGULATE TERMINAL 1, 1.5, 2, AND 3 AS ONE BUILDING. 2- RECLASSIFY T1 BAGGAGE HANDLING AREA FROM OCCUPANCY S TO F-1 3- NEW TERMINAL CONNECTION BETWEEN EXISTING T1.5 AND T2 AT LEVEL 02 DEPARTURES 4- RECONFIGURATION AND RELOCATION OF THE MPOE ROOM AT TERMINAL 2 LEVEL 01 ARRIVALS
Permit Issued
Issued on 9/15/2025
Issuing Office
Current Status
Issued on 9/15/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/17/2025 APPLICANT
Assigned to Plan Check Engineer 6/18/2025 FARSHAD ALIMOHAMADI
Corrections Issued 7/1/2025 FARSHAD ALIMOHAMADI
Quality Review Completed 7/8/2025 LIPING TENG
Applicant returned to address corrections 8/7/2025 FARSHAD ALIMOHAMADI
Applicant returned to address corrections 8/27/2025 FARSHAD ALIMOHAMADI
Plan Check Approved 9/4/2025 FARSHAD ALIMOHAMADI
Issued 9/15/2025 APPLICANT

Permit Application Clearance Information

City owned building/parcel Cleared 6/24/2025 MASON NG
Green Code Cleared 7/9/2025 Lily Teng
Airport buildings Cleared 8/26/2025 ANDREW KO
Fire Marshal Fire Life Safety Cleared 8/26/2025 ANDREW KO
DAS Clearance Cleared 8/28/2025 Lily Teng

Contact Information

Architect Ameen,, Farooq; Lic. No.: NA27196       ,
Contractor Mata Construction Services Inc; Lic. No.: 842965-B       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/6/2025 Approved NICK LAROCCA
Wall Anchors 11/6/2025 Approved NICK LAROCCA
Drywall Nailing 12/1/2025 Partial Approval NICK LAROCCA
Excavation/Setback/Form/Re-Bar 12/9/2025 Partial Approval NICK LAROCCA
Green Building Rough 12/9/2025 Approved NICK LAROCCA
Reinforced Concrete Frame 12/9/2025 Partial Inspection NICK LAROCCA
Light Gage Steel Frame 12/17/2025 Partial Approval NICK LAROCCA
Light Gage Steel Frame 1/5/2026 Partial Approval NICK LAROCCA
Light Gage Steel Frame 1/13/2026 Partial Approval NICK LAROCCA
Structural Steel Frame 1/21/2026 Approved NICK LAROCCA
T-Bar Ceiling 1/22/2026 Not Ready for Inspection RICARDO ROBLES
T-Bar Ceiling 1/23/2026 Not Ready for Inspection RICARDO ROBLES
T-Bar Ceiling 2/9/2026 Partial Approval NICK LAROCCA
Light Gage Steel Frame 2/26/2026 Corrections Issued NICK LAROCCA
Light Gage Steel Frame 3/23/2026 Partial Approval NICK LAROCCA