6362 N VAN NUYS BLVD 91401
Certificate Information: 6362 N VAN NUYS BLVD 91401
- Application / Permit
- 25016-10000-17648
- Plan Check / Job No.
- B25LA22633
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TI TO EXISTING RETAIL
- Permit Issued
- Issued on 1/22/2026
- Issuing Office
- Valley
- Current Status
- Issued on 1/22/2026
Permit Application Status History
| Submitted | 5/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2025 | FERNANDO FLORES |
| Corrections Issued | 6/6/2025 | FERNANDO FLORES |
| Building Plans Picked Up | 6/18/2025 | APPLICANT |
| Plan Check Approved | 10/3/2025 | SUNMIN LEE |
| Issued | 1/22/2026 | APPLICANT |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/30/2025 | BRENNEN OBETO |
| Supp. Use District POD/CDO/TDO | Cleared | 8/13/2025 | ROSALINDA MEZA |
Contact Information
| Contractor | West Side Developers Inc; Lic. No.: 1005034-B | 24007 VENTURA BLVD SUITE 285 CALABASAS, CA 91302 |
| Engineer | Danialian,, Derik; Lic. No.: C94256 | 15904 INDEX ST. GRANADA HILLS, CA 91344 |
Inspector Information
| SEAN GRIFFITH, (818) 374-1102 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/29/2026 | Not Ready for Inspection | GREGORY POMISH |
| Pre-Inspection | 2/3/2026 | Partial Inspection | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 3/17/2026 | Conditional Approval | SEAN GRIFFITH |
| Deputy Reinf. Concrete | 3/17/2026 | Conditional Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 3/19/2026 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Reinf. Concrete | 3/20/2026 | Conditional Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 3/25/2026 | Partial Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 4/2/2026 | Not Ready for Inspection | SEAN GRIFFITH |
| Deputy Reinf. Masonry | 4/3/2026 | Conditional Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 4/3/2026 | Partial Approval | SEAN GRIFFITH |
| Deputy Reinf. Concrete | 4/14/2026 | Conditional Approval | SEAN GRIFFITH |
| Deputy Reinf. Masonry | 4/14/2026 | Conditional Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 4/15/2026 | Partial Approval | SEAN GRIFFITH |
| Deputy Reinf. Concrete | 4/16/2026 | Conditional Approval | SEAN GRIFFITH |
| Deputy Reinf. Masonry | 4/16/2026 | Conditional Approval | SEAN GRIFFITH |
| Deputy Reinf. Concrete | 4/17/2026 | Conditional Approval | SEAN GRIFFITH |
| Deputy Reinf. Masonry | 4/17/2026 | Conditional Approval | SEAN GRIFFITH |
| Footing/Foundation/Slab | 4/23/2026 | Partial Approval | SEAN GRIFFITH |
| Wood Frame | 4/30/2026 | Not Ready for Inspection | SEAN GRIFFITH |
| Footing/Foundation/Slab | 5/8/2026 | Not Ready for Inspection | SEAN GRIFFITH |
| Wood Frame | 5/8/2026 | Partial Approval | SEAN GRIFFITH |
| Insulation | 5/12/2026 | Partial Approval | SEAN GRIFFITH |
| Drywall Nailing | 5/18/2026 | Not Ready for Inspection | SEAN GRIFFITH |
| Wood Frame | 5/18/2026 | Not Ready for Inspection | SEAN GRIFFITH |
| Drywall Nailing | 5/27/2026 | Partial Approval | SEAN GRIFFITH |
| Insulation | 6/5/2026 | Partial Approval | SEAN GRIFFITH |
| Drywall Nailing | 6/9/2026 | Partial Approval | SEAN GRIFFITH |