5138-5138 1/2 E RAPHAEL ST 90042

Certificate Information: 5138-5138 1/2 E RAPHAEL ST 90042

Application / Permit
25016-10000-17580
Plan Check / Job No.
B25LA22527
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERSION OF EXISTING UNINHABITED CRAWL SPACE TO JADU ADDITION (364 SF) TO EXISTING 1 STORY SFD PER GC 66323(a)(1) and 66333, SEE COMMENTS
Permit Issued
Issued on 8/15/2025
Issuing Office
Metro
Current Status
CofO Issued on 1/27/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2025 APPLICANT
Assigned to Plan Check Engineer 6/5/2025 STARR CHEN
Corrections Issued 6/10/2025 STARR CHEN
Quality Review Completed 6/10/2025 EUGENE BARBEAU
Applicant returned to address corrections 7/22/2025 STARR CHEN
Plan Check Approved 8/15/2025 STARR CHEN
Issued 8/15/2025 APPLICANT
CofO in Progress 1/26/2026 NICHOLAS LOPEZ
Permit Finaled 1/27/2026 DEROLD HAUFF
CofO Issued 1/27/2026 DEROLD HAUFF
Permit Finaled 1/27/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/28/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 6/28/2025 COLIN LOREDO
Sewer availability Cleared 6/28/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 7/1/2025 COLIN LOREDO
Hydrant and Access approval Cleared 7/11/2025 LAVEON RIDER
Grading Pre-Inspection Cleared 8/15/2025 RAMAZANALI ALMASI

Contact Information

Contractor Owner-Builder       ,
Engineer Nishimura,, Kentaro; Lic. No.: C73821 5138 RAPHAEL ST      LOS ANGELES, CA 90042

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 9/15/2025 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 9/17/2025 Corrections Issued BRENDAN MORELLI
Green Building Rough 9/17/2025 Not Ready for Inspection BRENDAN MORELLI
PLUMBING-Rough 9/17/2025 Approved BRENDAN MORELLI
BUILDING-Rough-Frame 10/7/2025 Conditional Approval NICHOLAS LOPEZ
ELECTRICAL-Rough 10/7/2025 Approved NICHOLAS LOPEZ
Green Building Rough 10/7/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 10/7/2025 Corrections Issued NICHOLAS LOPEZ
Insulation 10/7/2025 Conditional Approval NICHOLAS LOPEZ
BUILDING-Rough-Frame 10/22/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 10/22/2025 Conditional Approval NICHOLAS LOPEZ
Insulation 10/22/2025 Approved NICHOLAS LOPEZ
Drywall Nailing 11/10/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 11/10/2025 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 11/10/2025 Not Ready for Inspection NICHOLAS LOPEZ
PLUMBING-Final 11/10/2025 Not Ready for Inspection NICHOLAS LOPEZ
ELECTRICAL-Final 1/9/2026 Corrections Issued NICHOLAS LOPEZ
Final 1/9/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 1/9/2026 Not Ready for Inspection NICHOLAS LOPEZ
HVAC-Final 1/9/2026 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 1/9/2026 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/9/2026 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 1/9/2026 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/21/2026 Approved NICHOLAS LOPEZ
Final 1/21/2026 Corrections Issued NICHOLAS LOPEZ
Green Building Final 1/21/2026 Approved NICHOLAS LOPEZ
HVAC-Final 1/21/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/21/2026 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/21/2026 SGSOV Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/26/2026 Approved NICHOLAS LOPEZ
Final 1/26/2026 OK to Issue CofO NICHOLAS LOPEZ
HVAC-Final 1/26/2026 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/26/2026 Approved NICHOLAS LOPEZ