9340 N LASAINE AVE 91325
Certificate Information: 9340 N LASAINE AVE 91325
- Application / Permit
- 25016-10000-17332
- Plan Check / Job No.
- B25LA22053
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR AND EXTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING
- Permit Issued
- Issued on 6/23/2025
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 12/23/2025
Permit Application Status History
| Submitted | 5/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/28/2025 | KELVIN CHUONG |
| Corrections Issued | 5/28/2025 | KELVIN CHUONG |
| Applicant returned to address corrections | 6/6/2025 | SHANGQIN XIE |
| Plan Check Approved | 6/18/2025 | DANIEL YIP |
| Issued | 6/23/2025 | APPLICANT |
| Permit Finaled | 12/23/2025 | KEVIN BERBERYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Bergin Construction; Lic. No.: 1086438-B | 22243 BASSETT ST CANOGA PARK, CA 91303 |
| Engineer | Mauricio,, Omar; Lic. No.: C87487 | 947 E MERCED AVE WEST COVINA, CA 91790 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 7/2/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Insulation | 7/2/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Wood Frame | 7/2/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 7/3/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Footing/Foundation/Slab | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| Piling/Pier/Caisson | 7/7/2025 | Approved | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| Wood Frame | 7/10/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/21/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Wood Frame | 7/21/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 7/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 7/30/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 8/1/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 8/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 8/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Rough-Elec/Plmb/HVAC | 8/18/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 8/20/2025 | Approved | LOUIS ESCOTO |
| Final | 12/23/2025 | Permit Finaled | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/23/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 12/23/2025 | Approved | KEVIN BERBERYAN |