16839 W MCCORMICK ST 91436

Certificate Information: 16839 W MCCORMICK ST 91436

Application / Permit
25016-10000-17188
Plan Check / Job No.
B25LA21807
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Detached 1-story garage conversion to ADU per GC 66323(a)(1)
Permit Issued
Issued on 7/14/2025
Issuing Office
Current Status
Issued on 7/14/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/31/2025 APPLICANT
Assigned to Plan Check Engineer 6/4/2025 DAVID CASTILLO
Corrections Issued 6/5/2025 DAVID CASTILLO
Applicant returned to address corrections 7/1/2025 DAVID CASTILLO
Plan Check Approved 7/7/2025 DAVID CASTILLO
Issued 7/14/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/18/2025 MICHAEL BROWN
Sewer availability Cleared 6/18/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/24/2025 MICHAEL BROWN
Roof/Waste drainage to street Cleared 6/30/2025 MICHAEL BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Dass,, Praveen Kumar; Lic. No.: C74200 2801 ALTON PARKWAY   #205    IRVINE, CA 92606

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Green Building Final 6/10/2026   
Final 6/10/2026   

Inspection Request History

PLUMBING-Rough 7/29/2025 Partial Inspection MORRIS JACKSON
Pre-Inspection 7/29/2025 Partial Inspection MORRIS JACKSON
Footing/Foundation/Slab 8/11/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 8/11/2025 Not Ready for Inspection THOMAS FINNILA
Sewer 8/11/2025 Not Ready for Inspection THOMAS FINNILA
Gas Test 8/13/2025 Partial Approval THOMAS FINNILA
PLUMBING-Rough 8/13/2025 Partial Approval THOMAS FINNILA
Pre-Inspection 8/13/2025 Partial Inspection THOMAS FINNILA
Footing/Foundation/Slab 8/20/2025 Corrections Issued THOMAS FINNILA
PLUMBING-Rough 8/20/2025 Not Ready for Inspection THOMAS FINNILA
Pre-Inspection 8/20/2025 Not Ready for Inspection THOMAS FINNILA
Deputy Drilled-In Anchors 8/28/2025 Conditional Approval THOMAS FINNILA
Deputy Drilled-In Anchors 9/4/2025 Conditional Approval THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/4/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 9/4/2025 Not Ready for Inspection THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/8/2025 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 9/11/2025 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 9/12/2025 Approved SEAN WIRCH
Pre-Inspection 10/1/2025 Partial Inspection SEAN WIRCH
Gas Test 1/15/2026 Not Ready for Inspection MORRIS JACKSON
Rough-Elec/Plmb/HVAC 1/15/2026 Not Ready for Inspection MORRIS JACKSON
ELECTRICAL-Rough 1/30/2026 Corrections Issued SEAN WIRCH
Floor/Roof Diaphrgm/Shear Wall 1/30/2026 Partial Approval SEAN WIRCH
BUILDING-Rough-Frame 2/13/2026 Corrections Issued SEAN WIRCH
ELECTRICAL-Rough 2/13/2026 Approved SEAN WIRCH
Green Building Rough 2/13/2026 Not Ready for Inspection SEAN WIRCH
PLUMBING-Rough 2/13/2026 Approved SEAN WIRCH
BUILDING-Rough-Frame 3/17/2026 Approved SEAN WIRCH
Green Building Rough 3/17/2026 Approved SEAN WIRCH
ELECTRICAL-Final 5/19/2026 Corrections Issued SEAN WIRCH
HVAC-Final 5/19/2026 Corrections Issued SEAN WIRCH
PLUMBING-Final 5/19/2026 Corrections Issued SEAN WIRCH
Final 5/29/2026 Not Ready for Inspection SEAN WIRCH
Green Building Final 5/29/2026 Corrections Issued SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Approved SEAN WIRCH
Smoke Detectors 5/29/2026 Approved SEAN WIRCH