4052 E CHEVY CHASE DR 90039
Certificate Information: 4052 E CHEVY CHASE DR 90039
- Application / Permit
- 25016-10000-17092
- Plan Check / Job No.
- B25LA21623
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Soft-Story seismic retrofit per LABC Chapter 93: Install Steel Cantilever Columns and Steel Moment Frame
- Permit Issued
- Issued on 7/19/2025
- Issuing Office
- Current Status
- Issued on 7/19/2025
Permit Application Status History
| Submitted | 5/27/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | HANS SANTIAGO |
| Corrections Issued | 6/2/2025 | HANS SANTIAGO |
| Quality Review Completed | 6/6/2025 | DANIEL CHAN |
| Plan Check Approved | 7/14/2025 | ANDREW SANTIAGO |
| Issued | 7/19/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 7/10/2025 | KORNEL LELEA |
Contact Information
| Contractor | Glendale Retrofit Inc; Lic. No.: 1074027-B | , |
| Engineer | Ebrahimian, Dehaghani, Mahdi; Lic. No.: NA86987 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/31/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| Deputy Steel/Welding | 8/11/2025 | Conditional Approval | RONALD JIMENEZ |
| Structural Steel Frame | 8/11/2025 | No Access for Inspection | RONALD JIMENEZ |
| Deputy Drilled-In Anchors | 8/12/2025 | Conditional Approval | DARRYL ARNOLD |
| Deputy Reinf. Concrete | 8/12/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 8/12/2025 | Approved | RONALD JIMENEZ |
| Structural Steel Frame | 8/12/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 8/12/2025 | Approved | RONALD JIMENEZ |
| Deputy Reinf. Concrete | 8/14/2025 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 8/25/2025 | Conditional Approval | DARRYL ARNOLD |
| Final | 9/23/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 9/23/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 9/23/2025 | Conditional Approval | DARRYL ARNOLD |