5443 W CARLTON WAY 90027
Certificate Information: 5443 W CARLTON WAY 90027
- Application / Permit
- 25016-10000-17067
- Plan Check / Job No.
- B25LA21604
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- ALTERATION TO (E) APARTMENT TO PROVIDE 4 MOBILITY & 2 SENSORY UNITS. ACCESSIBILITY UPGRADES.
- Permit Issued
- Issued on 10/9/2025
- Issuing Office
- Current Status
- CofO in Progress on 7/21/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 6/26/2025 | KEVIN MORALES |
| Corrections Issued | 7/10/2025 | KEVIN MORALES |
| Quality Review Completed | 7/10/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 9/3/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 9/4/2025 | KEVIN MORALES |
| Applicant returned to address corrections | 9/23/2025 | KEVIN MORALES |
| Plan Check Approved | 10/8/2025 | KEVIN MORALES |
| Issued | 10/9/2025 | APPLICANT |
| CofO in Progress | 7/21/2026 | CHRISTOPHER BLACKWOOD |
Permit Application Clearance Information
| DAS Clearance | Cleared | 8/5/2025 | Mohammad Esmaili |
| Public Housing | Cleared | 8/13/2025 | JORGE ALCANTAR |
| Green Code | Cleared | 8/15/2025 | Mohammad Esmaili |
| Specific Plan | Cleared | 8/27/2025 | YAMILLET BRIZUELA |
Contact Information
| Architect | Kuchenski,, Stephen Ainsworth; Lic. No.: NA21218 | , |
| Contractor | Walton Construction Inc; Lic. No.: 1034491-B | , |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/13/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 11/19/2025 | Partial Approval | LUIS CCAMACHO |
| Insulation | 12/5/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Pre-Inspection | 12/5/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Wood Frame | 12/5/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Insulation | 12/9/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Light Gage Steel Frame | 12/9/2025 | Not Ready for Inspection | LUIS CCAMACHO |
| Wood Frame | 12/9/2025 | Partial Approval | LUIS CCAMACHO |
| Drywall Nailing | 12/11/2025 | Partial Approval | LUIS CCAMACHO |
| Wood Frame | 1/13/2026 | Partial Approval | EDWIN GREGORYONA |
| Final | 1/21/2026 | Partial Inspection | LUIS CCAMACHO |
| Green Building Final | 1/21/2026 | Not Ready for Inspection | LUIS CCAMACHO |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | LUIS CCAMACHO |
| Smoke Detectors | 1/21/2026 | Approved | LUIS CCAMACHO |
| Final | 2/25/2026 | Partial Inspection | LUIS CCAMACHO |
| Green Building Final | 2/25/2026 | Approved | LUIS CCAMACHO |
| Final | 7/1/2026 | Not Ready for Inspection | CHRISTOPHER BLACKWOOD |
| Final | 7/21/2026 | OK to Issue CofO | CHRISTOPHER BLACKWOOD |