11928 W DARLINGTON AVE 90049
Certificate Information: 11928 W DARLINGTON AVE 90049
- Application / Permit
- 25016-10000-16708
- Plan Check / Job No.
- B25LA20908
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install (4) New Special Steel Cantilever Columns.
- Permit Issued
- Issued on 11/14/2025
- Issuing Office
- Current Status
- CofC Issued on 4/7/2026
Permit Application Status History
| Submitted | 5/21/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/29/2025 | HANS SANTIAGO |
| Corrections Issued | 6/2/2025 | HANS SANTIAGO |
| Quality Review Completed | 6/6/2025 | DANIEL CHAN |
| Applicant returned to address corrections | 6/12/2025 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/31/2025 | HANS SANTIAGO |
| Plan Check Approved | 9/2/2025 | ANDREW SANTIAGO |
| Issued | 11/14/2025 | APPLICANT |
| OK for CofC | 4/7/2026 | VASIL MIHALEV |
| CofC Issued | 4/7/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 11/13/2025 | ARIC DEFUSCO |
Contact Information
| Contractor | One Stop Retrofit; Lic. No.: 1026051-B | , |
| Engineer | Alexander,, Andy; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 12/15/2025 | Approved | DARRYL ARNOLD |
| Final | 12/18/2025 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/18/2025 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/18/2025 | Corrections Issued | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/15/2026 | Conditional Approval | DARRYL ARNOLD |
| Deputy Wood Construction | 1/21/2026 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 1/22/2026 | Corrections Issued | DARRYL ARNOLD |
| Wood Frame | 1/23/2026 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 1/29/2026 | Approved | DANIEL VARNUM |
| Final | 3/13/2026 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 3/13/2026 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 3/20/2026 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 3/20/2026 | No Access for Inspection | DANIEL VARNUM |
| Final | 4/6/2026 | Partial Inspection | DANIEL VARNUM |
| Final | 4/7/2026 | OK for CofC | VASIL MIHALEV |
| SGSOV-Seismic Gas S/O Valve | 4/7/2026 | SGSOV Approved | VASIL MIHALEV |
| Smoke Detectors | 4/7/2026 | Approved | VASIL MIHALEV |