1255-1257 W GAGE AVE 90044
Certificate Information: 1255-1257 W GAGE AVE 90044
- Application / Permit
- 25016-10000-15948
- Plan Check / Job No.
- B25LA19823
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN: CONVERT SECOND FLOOR PORTION OF (E) SFD TO (N) 1108 SF ADU PER GCS66323(a)(1). CREATE A NEW DOOR OPENING FOR SFD, ALL WORK PER WFPP.
- Permit Issued
- Issued on 5/31/2025
- Issuing Office
- Current Status
- CofO Issued on 8/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/20/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 5/31/2025 | LUISANGEL VALENZUELA |
| Issued | 5/31/2025 | APPLICANT |
| CofO in Progress | 7/24/2025 | BARRY HACHE |
| Permit Finaled | 8/3/2025 | DEROLD HAUFF |
| CofO Issued | 8/3/2025 | DEROLD HAUFF |
| Permit Finaled | 8/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/27/2025 | DERRICK MAGEE |
| Sewer availability | Cleared | 5/27/2025 | DERRICK MAGEE |
| Eng Process Fee Ord 176,300 | Cleared | 5/28/2025 | DERRICK MAGEE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/25/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Rough | 6/25/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Rough | 6/25/2025 | Corrections Issued | BARRY HACHE |
| Wood Frame | 6/25/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Rough | 6/30/2025 | Not Ready for Inspection | BARRY HACHE |
| HVAC-Rough | 6/30/2025 | Not Ready for Inspection | BARRY HACHE |
| PLUMBING-Rough | 6/30/2025 | Corrections Issued | BARRY HACHE |
| BUILDING-Rough-Frame | 7/2/2025 | Approved | BARRY HACHE |
| ELECTRICAL-Rough | 7/2/2025 | Approved | BARRY HACHE |
| HVAC-Rough | 7/2/2025 | Approved | BARRY HACHE |
| Insulation | 7/2/2025 | Approved | BARRY HACHE |
| PLUMBING-Rough | 7/2/2025 | Approved | BARRY HACHE |
| Drywall Nailing | 7/10/2025 | Approved | REGINA MENDEZ |
| Final | 7/17/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | BARRY HACHE |
| Final | 7/22/2025 | Corrections Issued | BARRY HACHE |
| HVAC-Final | 7/22/2025 | Approved | BARRY HACHE |
| PLUMBING-Final | 7/22/2025 | Approved | BARRY HACHE |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | BARRY HACHE |
| Smoke Detectors | 7/22/2025 | Not Ready for Inspection | BARRY HACHE |
| ELECTRICAL-Final | 7/24/2025 | Approved | BARRY HACHE |
| Final | 7/24/2025 | OK to Issue CofO | BARRY HACHE |
| Smoke Detectors | 7/24/2025 | Approved | BARRY HACHE |