1802 W 41ST DR 90062
Certificate Information: 1802 W 41ST DR 90062
- Application / Permit
- 25016-10000-15947
- Plan Check / Job No.
- B25LA19817
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DET GARAGE INTO A (N) 400 SF ADU PER GCS 66323(a)(1), ALL WORK PER ENG.
- Permit Issued
- Issued on 9/1/2025
- Issuing Office
- Current Status
- Issued on 9/1/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/20/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 7/16/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/29/2025 | LUISANGEL VALENZUELA |
| Issued | 9/1/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/29/2025 | JEREMY CHOK |
| Sewer availability | Cleared | 6/29/2025 | JEREMY CHOK |
| Eng Process Fee Ord 176,300 | Cleared | 7/1/2025 | JEREMY CHOK |
| HPOZ | Cleared | 7/7/2025 | RAFAEL FONTES |
| Historic monument | Cleared | 7/7/2025 | RAFAEL FONTES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Klein,, Ross Hampton; Lic. No.: C82126 | 13331 MOORPARK ST UNIT 122 SHERMAN OAKS, CA 91423 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/1/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 10/23/2025 | Partial Approval | SABAS ALONSO |
| PLUMBING-Rough | 11/12/2025 | Approved | SABAS ALONSO |
| Sewer | 11/12/2025 | Approved | SABAS ALONSO |
| Underground Mechanical | 11/12/2025 | Corrections Issued | SABAS ALONSO |
| ELECTRICAL-Rough | 1/22/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2026 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 3/26/2026 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 3/31/2026 | Conditional Approval | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2026 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 4/1/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/1/2026 | Partial Approval | SABAS ALONSO |
| Underground Mechanical | 4/1/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2026 | Approved | SABAS ALONSO |
| Insulation | 4/27/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/27/2026 | Approved | SABAS ALONSO |
| Drywall Nailing | 4/29/2026 | Approved | SABAS ALONSO |