4326 N STILLWELL AVE 90032
Certificate Information: 4326 N STILLWELL AVE 90032
- Application / Permit
- 25016-10000-15616
- Plan Check / Job No.
- B25LA19435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT DETACHED 520 SF GARAGE TO ADU PER GC 66323(a)(1)
- Permit Issued
- Issued on 9/11/2025
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/19/2025 | SAMUEL GONZALEZ |
| Corrections Issued | 5/20/2025 | SAMUEL GONZALEZ |
| Plan Check Approved | 6/8/2025 | SAMUEL GONZALEZ |
| Issued | 9/11/2025 | APPLICANT |
| CofO in Progress | 4/28/2026 | LILIANA PORTILLO |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/21/2025 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 5/21/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/21/2025 | SAFA JAVANMARDI |
| "D" conditions | Cleared | 5/22/2025 | ROSALINDA MEZA |
| "Q" conditions | Cleared | 5/22/2025 | ROSALINDA MEZA |
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2025 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 6/3/2025 | MICHAEL TEMPLE |
Contact Information
| Contractor | American Tech Construction; Lic. No.: 662300-B | , |
| Engineer | Liu,, Frank; Lic. No.: C64806 | PO BOX 212 ARTESIA, CA 90702 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/26/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 9/26/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/3/2025 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 10/7/2025 | Approved | DAVID WILLIAMS |
| Deputy Drilled-In Anchors | 10/20/2025 | Conditional Approval | DAVID WILLIAMS |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 11/26/2025 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Rough | 11/26/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 11/26/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Rough | 12/2/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 12/9/2025 | Corrections Issued | RONNIE MEDINA |
| Green Building Rough | 12/9/2025 | Not Ready for Inspection | RONNIE MEDINA |
| Insulation | 12/9/2025 | Corrections Issued | RONNIE MEDINA |
| BUILDING-Rough-Frame | 12/12/2025 | Approved | LILIANA PORTILLO |
| Green Building Rough | 12/12/2025 | Approved | LILIANA PORTILLO |
| Insulation | 12/12/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/12/2025 | Partial Approval | LILIANA PORTILLO |
| Drywall Nailing | 12/22/2025 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 12/22/2025 | Approved | LILIANA PORTILLO |
| Shower Pan | 12/22/2025 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 2/24/2026 | Approved | LILIANA PORTILLO |
| Final | 4/2/2026 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Final | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Green Building Final | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| HVAC-Final | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Final | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Not Ready | DAVID WILLIAMS |
| Smoke Detectors | 4/21/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Final | 4/27/2026 | Approved | LILIANA PORTILLO |
| Final | 4/27/2026 | OK to Issue CofO | LILIANA PORTILLO |
| Green Building Final | 4/27/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 4/27/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 4/27/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 4/27/2026 | SGSOV No Gas | LILIANA PORTILLO |
| Service/Power Release | 4/27/2026 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 4/27/2026 | Approved | LILIANA PORTILLO |