1572 S KELTON AVE 90024

Certificate Information: 1572 S KELTON AVE 90024

Application / Permit
25016-10000-15498
Plan Check / Job No.
B25LA19288
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Eplan. Convert existing attached garage within duplex (per 24010-10000-01575) to new ADU per State Law
Permit Issued
Issued on 9/28/2025
Issuing Office
Current Status
Issued on 9/28/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/12/2025 APPLICANT
Assigned to Plan Check Engineer 5/15/2025 NEHEMIAS RAMOS
Corrections Issued 5/16/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 6/27/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 8/7/2025 NEHEMIAS RAMOS
Applicant returned to address corrections 9/17/2025 NEHEMIAS RAMOS
Plan Check Approved 9/26/2025 NEHEMIAS RAMOS
Issued 9/28/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 6/24/2025 MATHEW QUAN
Address approval Cleared 7/1/2025 XOCHITL ARQUIETA
Sewer availability Cleared 7/1/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 7/10/2025 JESSICA OPINION
Specific Plan Cleared 7/23/2025 HAMID GHAEMMAGHAMI
Miscellaneous Cleared 9/24/2025 XOCHITL ARQUIETA

Contact Information

Contractor Elm Construction; Lic. No.: 1099704-B       ,
Contractor Elm Group La Inc; Lic. No.: 1099704-B       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/3/2025 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 12/9/2025 Partial Approval MICHAEL ALLEN
Special/Order Compliance 12/9/2025 Approved MICHAEL ALLEN
Interior/Exterior Lathing 1/14/2026 Approved MICHAEL ALLEN
Special/Order Compliance 1/14/2026 Corrections Issued MICHAEL ALLEN
Green Building Rough 2/2/2026 Approved MICHAEL ALLEN
Wood Frame 2/2/2026 Conditional Approval MICHAEL ALLEN
Insulation 2/26/2026 Corrections Issued WILBER ROSALES
Insulation 3/4/2026 Approved RYAN SALAZAR
Drywall Nailing 3/6/2026 Approved MICHAEL ALLEN
Interior/Exterior Lathing 3/17/2026 Approved MICHAEL ALLEN