4712 S MARSHALL DR 90230
Certificate Information: 4712 S MARSHALL DR 90230
- Application / Permit
- 25016-10000-15449
- Plan Check / Job No.
- B25LA19216
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
- Permit Issued
- Issued on 9/30/2025
- Issuing Office
- Current Status
- Issued on 9/30/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/13/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2025 | GIOVANNY CHAVEZ |
| Corrections Issued | 5/19/2025 | GIOVANNY CHAVEZ |
| Applicant returned to address corrections | 7/29/2025 | GIOVANNY CHAVEZ |
| Plan Check Approved | 9/30/2025 | GIOVANNY CHAVEZ |
| Issued | 9/30/2025 | APPLICANT |
Permit Application Clearance Information
| Specific Plan | Cleared | 5/20/2025 | HAMID GHAEMMAGHAMI |
| Address approval | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/22/2025 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 7/21/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 7/21/2025 | RIDWAN HARDY |
Contact Information
| Architect | Nichols,, Mark; Lic. No.: NA38099 | , |
| Contractor | Socal Canyon Builders Inc; Lic. No.: 1116958-B | , |
| Engineer | Meleika,, Samuel H; Lic. No.: C86049 | 5225 CANYON CREST DR. STE 71 #137 RIVERSIDE RIVERSIDE, CA 92507 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/23/2025 | Approved | WILBER ROSALES |
| Underground Mechanical | 10/23/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 3/2/2026 | Not Ready for Inspection | HERBERT GIRON |
| ELECTRICAL-Rough | 3/2/2026 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 3/2/2026 | Not Ready for Inspection | HERBERT GIRON |
| HVAC-Rough | 3/2/2026 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 3/2/2026 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 3/18/2026 | Approved | ANTHONY EGSON |
| HVAC-Rough | 3/18/2026 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 3/18/2026 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 3/26/2026 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 4/9/2026 | Approved | DAKOTA LOW |
| Green Building Rough | 4/9/2026 | Approved | DAKOTA LOW |
| Insulation | 4/9/2026 | Approved | DAKOTA LOW |
| Drywall Nailing | 4/15/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 6/2/2026 | Approved | MORRIS JACKSON |
| Sewer | 6/2/2026 | Approved | MORRIS JACKSON |