17148-17150 W MAYALL ST 91325

Certificate Information: 17148-17150 W MAYALL ST 91325

Application / Permit
25016-10000-15255
Plan Check / Job No.
B25VN09942
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN: REMODEL SFD AND CONVERT ATTACHTED GARAGE INTO JADU PER GC 66323(a)(1) & 66333
Permit Issued
Issued on 7/8/2025
Issuing Office
Current Status
CofO Issued on 6/26/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/10/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 JESSE VIDUYA
Corrections Issued 5/9/2025 JESSE VIDUYA
Quality Review Completed 5/20/2025 GARO TELMI
Applicant returned to address corrections 7/2/2025 JESSE VIDUYA
Plan Check Approved 7/8/2025 JESSE VIDUYA
Issued 7/8/2025 APPLICANT
CofO in Progress 4/22/2026 JENNIFER RABUCHIN
Permit Finaled 6/26/2026 RUBEN SALAS
CofO Issued 6/26/2026 RUBEN SALAS
Permit Finaled 6/26/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/30/2025 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 5/30/2025 RYAN CASTRO
Sewer availability Cleared 5/30/2025 RYAN CASTRO
Grading Pre-Inspection Cleared 7/2/2025 JESSE VIDUYA

Contact Information

Contractor Owner-Builder       ,
Engineer Zolfaghari,, Saeed; Lic. No.: C86761 6201 BEE AVE      AGOURA HILLS, CA 91301

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/23/2025 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 7/25/2025 Approved CHRISTOPHER ROJAS
Footing/Foundation/Slab 7/25/2025 Approved CHRISTOPHER ROJAS
Sewer 7/25/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 7/25/2025 Corrections Issued CHRISTOPHER ROJAS
Underground Mechanical 7/28/2025 Partial Approval NICHOLAS TROWBRIDGE
Deputy Reinf. Concrete 7/29/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 9/4/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/17/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 10/8/2025 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 10/20/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/27/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 10/27/2025 Approved NICHOLAS TROWBRIDGE
Green Building Rough 10/27/2025 Approved NICHOLAS TROWBRIDGE
Insulation 11/3/2025 Approved CHRISTOPHER ROJAS
Drywall Nailing 11/18/2025 Approved NICHOLAS TROWBRIDGE
Shower Pan 11/21/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 12/10/2025 Approved KEVIN BERBERYAN
Underground Mechanical 12/10/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 3/31/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/6/2026 Approved DAVID MATSON
Service/Power Release 4/6/2026 Not Ready for Inspection DAVID MATSON
ELECTRICAL-Final 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
Final 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 4/10/2026 Approved CHRISTOPHER ROJAS
HVAC-Final 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 4/10/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 4/10/2026 SGSOV Approved CHRISTOPHER ROJAS
Smoke Detectors 4/10/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/15/2026 Approved WAYNE REGESTER
Final 4/15/2026 Corrections Issued WAYNE REGESTER
HVAC-Final 4/15/2026 Approved WAYNE REGESTER
PLUMBING-Final 4/15/2026 Approved WAYNE REGESTER
Service/Power Release 4/15/2026 Approved WAYNE REGESTER
Final 4/22/2026 OK to Issue CofO JENNIFER RABUCHIN