1625 W 248TH ST 90710

Certificate Information: 1625 W 248TH ST 90710

Application / Permit
25016-10000-15236
Plan Check / Job No.
B25LA19004
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) DETACHED GARAGE INTO ADU PER GC 66323(a)(1) PER WFPP
Permit Issued
Issued on 9/11/2025
Issuing Office
Current Status
CofO Issued on 4/24/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/10/2025 APPLICANT
Assigned to Plan Check Engineer 5/14/2025 JOHNPAUL ISIP
Corrections Issued 5/15/2025 JOHNPAUL ISIP
Applicant returned to address corrections 8/21/2025 JOHNPAUL ISIP
Plan Check Approved 8/27/2025 JOHNPAUL ISIP
Issued 9/11/2025 APPLICANT
CofO in Progress 4/23/2026 EUGENE CASSIDY
Permit Finaled 4/24/2026 ANSON MAGLASANG
CofO Issued 4/24/2026 ANSON MAGLASANG
Permit Finaled 4/24/2026 ANSON MAGLASANG

Permit Application Clearance Information

Construction near power lines Cleared 7/25/2025 RIDWAN HARDY
Address approval Cleared 7/29/2025 XOCHITL ARQUIETA
Eng Process Fee Ord 176,300 Cleared 7/29/2025 XOCHITL ARQUIETA
Sewer availability Cleared 8/25/2025 XOCHITL ARQUIETA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 10/7/2025 Approved EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 11/3/2025 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Rough 11/18/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 11/18/2025 Approved EUGENE CASSIDY
HVAC-Rough 12/8/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 12/8/2025 Partial Approval EUGENE CASSIDY
Insulation 12/12/2025 Approved EUGENE CASSIDY
Insulation 12/18/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 12/23/2025 Not Ready for Inspection EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 12/23/2025 Approved EUGENE CASSIDY
Green Building Rough 12/23/2025 Approved EUGENE CASSIDY
METHANE-Rough 12/23/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 1/12/2026 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 3/12/2026 Approved EUGENE CASSIDY
Final 3/12/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 3/12/2026 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 3/12/2026 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 3/12/2026 Approved EUGENE CASSIDY
Final 4/8/2026 Corrections Issued EUGENE CASSIDY
ELECTRICAL-Final 4/22/2026 Approved EUGENE CASSIDY
Final 4/22/2026 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 4/22/2026 Approved EUGENE CASSIDY
PLUMBING-Final 4/22/2026 Approved EUGENE CASSIDY