3227-3227 1/2 E 3RD ST 90063
Certificate Information: 3227-3227 1/2 E 3RD ST 90063
- Application / Permit
- 25016-10000-15184
- Plan Check / Job No.
- B25LA14661
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- EPLAN: CONVERT (E) 1-STORY SFD TO DUPLEX
- Permit Issued
- Issued on 8/20/2025
- Issuing Office
- Current Status
- Issued on 8/20/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | JESSE VIDUYA |
| Corrections Issued | 5/9/2025 | JESSE VIDUYA |
| Quality Review Completed | 5/20/2025 | CHAD DOI |
| Applicant returned to address corrections | 7/18/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 7/29/2025 | JESSE VIDUYA |
| Applicant returned to address corrections | 8/8/2025 | JESSE VIDUYA |
| Plan Check Approved | 8/19/2025 | JESSE VIDUYA |
| Issued | 8/20/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2025 | MICHAEL BROWN |
| Roof/Waste drainage to street | Cleared | 5/29/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/29/2025 | MICHAEL BROWN |
| Low Impact Development (LID) | Cleared | 7/21/2025 | ERNEST TSE |
| Grading Pre-Inspection | Cleared | 8/19/2025 | JESSE VIDUYA |
Contact Information
| Contractor | Bpc Development Inc; Lic. No.: 1059885-B | , |
| Contractor | Builder Point Construction; Lic. No.: 1059885-B | , |
| Engineer | Sarrami,, Gholamali F; Lic. No.: C43720 | 4942 HIGHLAND VIEW AVENUE LOS ANGELES, CA 90041 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| Service/Power Release | 6/8/2026 |
| ELECTRICAL-Final | 6/8/2026 |
| Gas Test | 6/8/2026 |
| SGSOV-Seismic Gas S/O Valve | 6/8/2026 |
| Smoke Detectors | 6/8/2026 |
| Final | 6/8/2026 |
Inspection Request History
| Footing/Foundation/Slab | 9/10/2025 | No Access for Inspection | FREDDIE RIVERA |
| Underground Mechanical | 9/10/2025 | No Access for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/18/2025 | Approved | FREDDIE RIVERA |
| Underground Mechanical | 9/18/2025 | Partial Inspection | FREDDIE RIVERA |
| Insulation | 10/9/2025 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2025 | Approved | DEVON JACKSON |
| PLUMBING-Rough | 11/10/2025 | No Access for Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 11/18/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/1/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 12/1/2025 | Approved | FREDDIE RIVERA |
| Rough-Elec/Plmb/HVAC | 12/1/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | FREDDIE RIVERA |
| ELECTRICAL-Rough | 12/4/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 12/4/2025 | Approved | FREDDIE RIVERA |
| Insulation | 12/9/2025 | No Access for Inspection | WILLIAM SIERRA |
| Insulation | 12/11/2025 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 12/19/2025 | Approved | JOHN QUINTANILLA |
| Shower Pan | 12/19/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Drywall Nailing | 12/24/2025 | Approved | FREDDIE RIVERA |
| HVAC-Final | 5/26/2026 | Corrections Issued | FREDDIE RIVERA |
| PLUMBING-Final | 5/26/2026 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Final | 6/5/2026 | No Result Entered | FREDDIE RIVERA |
| PLUMBING-Final | 6/5/2026 | No Result Entered | FREDDIE RIVERA |