10821 W WELLWORTH AVE 90024

Certificate Information: 10821 W WELLWORTH AVE 90024

Application / Permit
25016-10000-15151
Plan Check / Job No.
B25LA18879
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED STORAGE AND WORKSHOP TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). WORK DONE PER ARCHITECT DESIGN.
Permit Issued
Issued on 7/21/2025
Issuing Office
Current Status
CofO Issued on 2/20/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/9/2025 APPLICANT
Assigned to Plan Check Engineer 5/13/2025 MADISON ODELL
Corrections Issued 5/14/2025 MADISON ODELL
Plan Check Approved 7/18/2025 MADISON O'DELL
Issued 7/21/2025 APPLICANT
CofO in Progress 2/20/2026 WILBER ROSALES
Permit Finaled 2/20/2026 RICHARD STEINBACH
CofO Issued 2/20/2026 RICHARD STEINBACH
Permit Finaled 2/20/2026 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 5/19/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 5/20/2025 MICHAEL BROWN
Sewer availability Cleared 5/20/2025 MICHAEL BROWN
Specific Plan Cleared 5/20/2025 EDER ROMERO
Grading Pre-Inspection Cleared 5/20/2025 LANNY MERRICK
Construction near power lines Cleared 7/3/2025 ENRIQUE ACOSTA
Construction within easement Cleared 7/3/2025 ENRIQUE ACOSTA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: NA21514       ,
Contractor Rahban Development; Lic. No.: 1089793-B       ,

Inspector Information

ANTHONY EGSON, (310) 914-3893 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/25/2025 Partial Inspection ARAM AVEDISIAN
Footing/Foundation/Slab 9/2/2025 Partial Approval SEAN HAUPT
BUILDING-Rough-Frame 10/14/2025 Conditional Approval MICHAEL ALLEN
ELECTRICAL-Rough 10/14/2025 Approved MICHAEL ALLEN
Footing/Foundation/Slab 10/14/2025 Approved MICHAEL ALLEN
Gas Test 10/14/2025 Approved MICHAEL ALLEN
Green Building Rough 10/14/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Rough 10/14/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Rough 10/14/2025 Approved MICHAEL ALLEN
HVAC-Rough 10/21/2025 Approved MICHAEL ALLEN
Underground Mechanical 10/21/2025 Approved MICHAEL ALLEN
Insulation 10/27/2025 Conditional Approval MICHAEL ALLEN
BUILDING-Rough-Frame 10/31/2025 Approved MICHAEL ALLEN
Floor/Roof Diaphrgm/Shear Wall 10/31/2025 Approved MICHAEL ALLEN
Green Building Rough 10/31/2025 Partial Approval MICHAEL ALLEN
Interior/Exterior Lathing 11/10/2025 Partial Approval MICHAEL ALLEN
Drywall Nailing 11/17/2025 Approved EVAN COOPER
Interior/Exterior Lathing 11/17/2025 Approved EVAN COOPER
Shower Pan 11/17/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 2/9/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/9/2026 Corrections Issued MICHAEL ALLEN
Final 2/9/2026 Corrections Issued MICHAEL ALLEN
Green Building Final 2/9/2026 Approved MICHAEL ALLEN
Green Building Rough 2/9/2026 Approved MICHAEL ALLEN
HVAC-Final 2/9/2026 Not Ready for Inspection MICHAEL ALLEN
PLUMBING-Final 2/9/2026 Approved MICHAEL ALLEN
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Approved MICHAEL ALLEN
Smoke Detectors 2/9/2026 Approved MICHAEL ALLEN
ELECTRICAL-Final 2/19/2026 Approved WILBER ROSALES
Final 2/19/2026 OK to Issue CofO WILBER ROSALES
HVAC-Final 2/19/2026 Approved WILBER ROSALES