10821 W WELLWORTH AVE 90024
Certificate Information: 10821 W WELLWORTH AVE 90024
- Application / Permit
- 25016-10000-15151
- Plan Check / Job No.
- B25LA18879
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED STORAGE AND WORKSHOP TO NEW ACCESSORY DWELLING UNIT PER GCS 66323(a)(1). WORK DONE PER ARCHITECT DESIGN.
- Permit Issued
- Issued on 7/21/2025
- Issuing Office
- Current Status
- CofO Issued on 2/20/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/13/2025 | MADISON ODELL |
| Corrections Issued | 5/14/2025 | MADISON ODELL |
| Plan Check Approved | 7/18/2025 | MADISON O'DELL |
| Issued | 7/21/2025 | APPLICANT |
| CofO in Progress | 2/20/2026 | WILBER ROSALES |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
| CofO Issued | 2/20/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/20/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/19/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/20/2025 | MICHAEL BROWN |
| Specific Plan | Cleared | 5/20/2025 | EDER ROMERO |
| Grading Pre-Inspection | Cleared | 5/20/2025 | LANNY MERRICK |
| Construction near power lines | Cleared | 7/3/2025 | ENRIQUE ACOSTA |
| Construction within easement | Cleared | 7/3/2025 | ENRIQUE ACOSTA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: NA21514 | , |
| Contractor | Rahban Development; Lic. No.: 1089793-B | , |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/25/2025 | Partial Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 9/2/2025 | Partial Approval | SEAN HAUPT |
| BUILDING-Rough-Frame | 10/14/2025 | Conditional Approval | MICHAEL ALLEN |
| ELECTRICAL-Rough | 10/14/2025 | Approved | MICHAEL ALLEN |
| Footing/Foundation/Slab | 10/14/2025 | Approved | MICHAEL ALLEN |
| Gas Test | 10/14/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 10/14/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| HVAC-Rough | 10/14/2025 | Partial Approval | MICHAEL ALLEN |
| PLUMBING-Rough | 10/14/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 10/21/2025 | Approved | MICHAEL ALLEN |
| Underground Mechanical | 10/21/2025 | Approved | MICHAEL ALLEN |
| Insulation | 10/27/2025 | Conditional Approval | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 10/31/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2025 | Approved | MICHAEL ALLEN |
| Green Building Rough | 10/31/2025 | Partial Approval | MICHAEL ALLEN |
| Interior/Exterior Lathing | 11/10/2025 | Partial Approval | MICHAEL ALLEN |
| Drywall Nailing | 11/17/2025 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 11/17/2025 | Approved | EVAN COOPER |
| Shower Pan | 11/17/2025 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/9/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/9/2026 | Corrections Issued | MICHAEL ALLEN |
| Final | 2/9/2026 | Corrections Issued | MICHAEL ALLEN |
| Green Building Final | 2/9/2026 | Approved | MICHAEL ALLEN |
| Green Building Rough | 2/9/2026 | Approved | MICHAEL ALLEN |
| HVAC-Final | 2/9/2026 | Not Ready for Inspection | MICHAEL ALLEN |
| PLUMBING-Final | 2/9/2026 | Approved | MICHAEL ALLEN |
| SGSOV-Seismic Gas S/O Valve | 2/9/2026 | SGSOV Approved | MICHAEL ALLEN |
| Smoke Detectors | 2/9/2026 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Final | 2/19/2026 | Approved | WILBER ROSALES |
| Final | 2/19/2026 | OK to Issue CofO | WILBER ROSALES |
| HVAC-Final | 2/19/2026 | Approved | WILBER ROSALES |