3114 S RAYMOND AVE 90007
Certificate Information: 3114 S RAYMOND AVE 90007
- Application / Permit
- 25016-10000-15150
- Plan Check / Job No.
- B25LA18878
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO A (N) 660 SF ADU PER GCS 66323(a)(4).
- Permit Issued
- Issued on 7/30/2025
- Issuing Office
- Current Status
- CofO Issued on 4/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/13/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 5/23/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 6/2/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 7/29/2025 | LUISANGEL VALENZUELA |
| Issued | 7/30/2025 | APPLICANT |
| CofO in Progress | 4/2/2026 | WILLIAM SIERRA |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
| CofO Issued | 4/2/2026 | DEROLD HAUFF |
| Permit Finaled | 4/2/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 5/14/2025 | MANERI ROMAN |
| Community Plan Implem. Overlay | Cleared | 5/14/2025 | MANERI ROMAN |
| Tenant Habitability Plan | Cleared | 5/16/2025 | RICARDO BOHORQUEZ |
| Address approval | Cleared | 5/19/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/19/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2025 | MICHAEL BROWN |
| ZI | Cleared | 6/20/2025 | DAVID URITA |
| Construction near power lines | Cleared | 7/25/2025 | RIDWAN HARDY |
Contact Information
| Contractor | New Beginning Construction Company Corp The; Lic. No.: 848904-B | , |
| Contractor | New Beginnning Construction Company The; Lic. No.: 848904-B | , |
| Engineer | Castillo,, Margarito; Lic. No.: NA4808 | , |
Inspector Information
| WILLIAM SIERRA, (213) 202-3122 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/13/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 8/14/2025 | Partial Approval | LUIS CASTRO |
| Pre-Inspection | 8/14/2025 | Corrections Issued | LUIS CASTRO |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 9/3/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| METHANE-Rough | 9/3/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Wood Frame | 9/3/2025 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Rough | 9/8/2025 | No Access for Inspection | ALFREDO LOPEZ |
| METHANE-Rough | 9/8/2025 | No Access for Inspection | ALFREDO LOPEZ |
| Wood Frame | 9/8/2025 | No Access for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2025 | Partial Approval | WILLIAM SIERRA |
| Green Building Rough | 9/12/2025 | Approved | WILLIAM SIERRA |
| METHANE-Rough | 9/12/2025 | Approved | WILLIAM SIERRA |
| Drywall Nailing | 1/16/2026 | Approved | WILLIAM SIERRA |
| Final | 1/16/2026 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 1/16/2026 | Approved | WILLIAM SIERRA |
| Smoke Detectors | 1/16/2026 | Corrections Issued | WILLIAM SIERRA |
| Wood Frame | 1/16/2026 | Approved | WILLIAM SIERRA |
| Final | 1/30/2026 | Corrections Issued | WILLIAM SIERRA |
| Smoke Detectors | 1/30/2026 | Approved | WILLIAM SIERRA |
| Final | 3/31/2026 | OK to Issue CofO | WILLIAM SIERRA |