3866 S WESTSIDE AVE 90008
Certificate Information: 3866 S WESTSIDE AVE 90008
- Application / Permit
- 25016-10000-14968
- Plan Check / Job No.
- B25LA18654
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Interior / exterior remodel to existing Single Family Dwelling
- Permit Issued
- Issued on 6/10/2025
- Issuing Office
- Current Status
- Permit Finaled on 11/25/2025
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | AMY GUEVARRA |
| Corrections Issued | 5/15/2025 | AMY GUEVARRA |
| Plan Check Approved | 6/1/2025 | REZA HAGHIGHAT |
| Issued | 6/10/2025 | APPLICANT |
| Permit Finaled | 11/24/2025 | LUIS CASTRO |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/16/2025 | ABEL CASILLAS |
| Sewer availability | Cleared | 5/16/2025 | ABEL CASILLAS |
Contact Information
| Architect | Zohrabians,, Arthur Hamayak; Lic. No.: C37490 | 700 PALM DR 106 GLENDALE, CA 91202 |
| Contractor | Settled Space Llc; Lic. No.: 1092313-B | , |
| Contractor | Taryn Ashley Homes; Lic. No.: 1092313-B | , |
| Engineer | Sayegh,, Elie; Lic. No.: NA88435 | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 8/6/2025 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/6/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/6/2025 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 8/6/2025 | Corrections Issued | SABAS ALONSO |
| PLUMBING-Rough | 8/8/2025 | Approved | MICHAEL LEWIS |
| HVAC-Rough | 8/21/2025 | Approved | MICHAEL LEWIS |
| Insulation | 8/28/2025 | Approved | ANTHONY RAMOS |
| BUILDING-Rough-Frame | 9/3/2025 | Partial Approval | LUIS CASTRO |
| Shower Pan | 9/3/2025 | Approved | LUIS CASTRO |
| Drywall Nailing | 9/9/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 9/9/2025 | Approved | RONNIE MEDINA |
| Interior/Exterior Lathing | 9/30/2025 | Approved | RONNIE MEDINA |
| ELECTRICAL-Final | 11/13/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 11/13/2025 | Approved | LUIS CASTRO |
| Final | 11/24/2025 | Permit Finaled | LUIS CASTRO |
| PLUMBING-Final | 11/24/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 11/24/2025 | SGSOV Approved | LUIS CASTRO |
| Smoke Detectors | 11/24/2025 | Approved | LUIS CASTRO |