20 E 29TH AVE 309 90291
Certificate Information: 20 E 29TH AVE 309 90291
- Application / Permit
- 25016-10000-14405
- Plan Check / Job No.
- B25LA17917
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- eplan. Fire damage repairs at an existing unit (UNIT 309 ON 3rd LEVEL)
- Permit Issued
- Issued on 6/2/2025
- Issuing Office
- Current Status
- Permit Finaled on 3/6/2026
Permit Application Status History
| Submitted | 5/5/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2025 | SARKIS HARABEDIAN |
| Corrections Issued | 5/12/2025 | SARKIS HARABEDIAN |
| Applicant returned to address corrections | 5/14/2025 | SARKIS HARABEDIAN |
| Plan Check Approved | 5/30/2025 | SARKIS HARABEDIAN |
| Issued | 6/2/2025 | APPLICANT |
| Permit Finaled | 3/6/2026 | FARHAD DADBIN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 5/27/2025 | KORNEL LELEA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yaprak,, Taskin Tolga; Lic. No.: C72927 | 562 31ST ST MANHATTAN BEACH, CA 90266 |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 7/31/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Wood Frame | 10/3/2025 | Partial Approval | FARHAD DADBIN |
| Pre-Inspection | 10/6/2025 | Partial Approval | FARHAD DADBIN |
| Insulation | 10/15/2025 | Conditional Approval | FARHAD DADBIN |
| Drywall Nailing | 11/14/2025 | Approved | FARHAD DADBIN |
| Final | 1/23/2026 | Not Ready for Inspection | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 1/23/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 1/23/2026 | Approved | FARHAD DADBIN |
| Final | 3/6/2026 | Permit Finaled | FARHAD DADBIN |