6842 N BERTRAND AVE 91335
Certificate Information: 6842 N BERTRAND AVE 91335
- Application / Permit
- 25016-10000-13928
- Plan Check / Job No.
- B25LA17423
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Enlarge existing ADU by converting attached garage to ADU per LAMC 12.22 A.33(b)(1). Design per WFPP.
- Permit Issued
- Issued on 6/17/2025
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2025 | CAROLEAN BASMA |
| Corrections Issued | 5/6/2025 | CAROLEAN BASMA |
| Plan Check Approved | 6/3/2025 | CAROLEAN BASMA |
| Issued | 6/17/2025 | APPLICANT |
| CofO in Progress | 1/5/2026 | ARUTYUN MADATYAN |
| Permit Finaled | 1/9/2026 | JOHN JANSON |
| CofO Issued | 1/9/2026 | JOHN JANSON |
| Permit Finaled | 1/9/2026 | JOHN JANSON |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Eden Development & Consulting Inc; Lic. No.: 984612-B | , |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/1/2025 | Approved | SEAN WIRCH |
| BUILDING-Rough-Frame | 7/24/2025 | Corrections Issued | ARUTYUN MADATYAN |
| ELECTRICAL-Rough | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Partial Approval | ARUTYUN MADATYAN |
| Green Building Rough | 7/24/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| HVAC-Rough | 7/24/2025 | Approved | ARUTYUN MADATYAN |
| Deputy Drilled-In Anchors | 7/25/2025 | Conditional Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 7/30/2025 | Partial Approval | JUAN ALVARADO |
| Green Building Rough | 7/30/2025 | Approved | JUAN ALVARADO |
| Interior/Exterior Lathing | 7/30/2025 | Approved | JUAN ALVARADO |
| PLUMBING-Rough | 7/30/2025 | Approved | JUAN ALVARADO |
| Insulation | 8/4/2025 | Approved | JUAN ALVARADO |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | GEVORK IPCHYAN |
| Drywall Nailing | 8/12/2025 | Approved | JUAN ALVARADO |
| BUILDING-Rough-Frame | 9/9/2025 | Approved | JUAN ALVARADO |
| Final | 9/9/2025 | Corrections Issued | JUAN ALVARADO |
| Green Building Final | 9/9/2025 | Approved | JUAN ALVARADO |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | JUAN ALVARADO |
| Smoke Detectors | 9/9/2025 | Approved | JUAN ALVARADO |
| Final | 9/29/2025 | Not Ready for Inspection | ARUTYUN MADATYAN |
| Final | 11/3/2025 | Corrections Issued | JUAN ALVARADO |
| Final | 12/26/2025 | OK to Issue CofO | ARUTYUN MADATYAN |