11561 W GATEWAY BLVD 90064

Certificate Information: 11561 W GATEWAY BLVD 90064

Application / Permit
25016-10000-13793
Plan Check / Job No.
B25LA17233
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(18) School Building
Work Description
Eplan. Replace (1) existing exterior stairway (Stair #2), same size and same location. Enclose area of 84 sq ft under one stair for storage space to be 1 hr rated.
Permit Issued
Issued on 6/24/2025
Issuing Office
Current Status
CofO Issued on 10/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2025 APPLICANT
Assigned to Plan Check Engineer 5/1/2025 HELEN NGUYEN
Assigned to Zoning Architect 5/2/2025 BENNY WONG
Corrections Issued 5/5/2025 HELEN NGUYEN
Quality Review Completed 5/6/2025 LAURA DUONG
Applicant returned to address corrections 6/10/2025 HELEN NGUYEN
Plan Check Approved 6/24/2025 HELEN NGUYEN
Issued 6/24/2025 APPLICANT
CofO in Progress 10/28/2025 FARHAD DADBIN
Permit Finaled 10/30/2025 DAVID TSAU
CofO Issued 10/30/2025 DAVID TSAU
Permit Finaled 10/30/2025 DAVID TSAU

Permit Application Clearance Information

CPC Cleared 5/13/2025 MAYELA VILLA
Green Code Cleared 5/13/2025 AARON COSTA
ZA Case Cleared 5/13/2025 MAYELA VILLA
ZA Case Cleared 5/13/2025 MAYELA VILLA
ZA Case Cleared 5/13/2025 MAYELA VILLA
Sewer availability Cleared 5/20/2025 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 5/21/2025 JEREMY CHOK
Specific Plan Cleared 5/21/2025 RICHARD WOO
Specific Plan Cleared 5/27/2025 KYLE WINSTON
Fire Marshal Fire Life Safety Cleared 6/15/2025 FIRE DEPARTMENT
DAS Clearance Cleared 6/16/2025 Cristina Salazar
Zoning Plan Check Cleared 6/17/2025 BENNY WONG

Contact Information

Architect , ; Lic. No.: C36976       ,
Contractor Blackwell Development Inc; Lic. No.: 1070521-B 13229 SEVENTH PLACE      YUCAIPA, CA 92399
Engineer Roi,, Jeffrey Steven; Lic. No.: S5849 3520 ENCINAL AVENUE      GLENDALE, CA 91214

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/1/2025 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 7/2/2025 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 7/9/2025 Approved FARHAD DADBIN
Deputy Reinf. Concrete 7/9/2025 Approved FARHAD DADBIN
Footing/Foundation/Slab 7/9/2025 Conditional Approval FARHAD DADBIN
Deputy Reinf. Concrete 7/11/2025 Conditional Approval FARHAD DADBIN
Deputy Drilled-In Anchors 7/22/2025 Conditional Approval FARHAD DADBIN
Light Gage Steel Frame 7/24/2025 No Access for Inspection FARHAD DADBIN
Light Gage Steel Frame 7/26/2025 Conditional Approval FARHAD DADBIN
Drywall Nailing 7/29/2025 Approved FARHAD DADBIN
Insulation 7/29/2025 Approved FARHAD DADBIN
Interior/Exterior Lathing 8/1/2025 Approved DANIEL VARNUM
Final 10/15/2025 Not Ready for Inspection FARHAD DADBIN
Green Building Final 10/15/2025 Approved FARHAD DADBIN
Green Building Rough 10/15/2025 Approved FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/15/2025 SGSOV Approved FARHAD DADBIN
Smoke Detectors 10/15/2025 Approved FARHAD DADBIN
Wood Frame 10/15/2025 Approved FARHAD DADBIN
Final 10/24/2025 Not Ready for Inspection FARHAD DADBIN
Final 10/28/2025 OK to Issue CofO FARHAD DADBIN