10020-10022 N DEBRA AVE 91343
Certificate Information: 10020-10022 N DEBRA AVE 91343
- Application / Permit
- 25016-10000-13729
- Plan Check / Job No.
- B25LA17180
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERSION OF (E) ATTACHED GARAGE TO STATE ADU PER GCS 66323(a)(1), ALL WORK PER WFPP
- Permit Issued
- Issued on 5/22/2025
- Issuing Office
- Current Status
- Issued on 5/22/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/29/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2025 | MINA HABILI |
| Corrections Issued | 5/3/2025 | MINA HABILI |
| Building Plans Picked Up | 5/6/2025 | APPLICANT |
| Plan Check Approved | 5/13/2025 | DANIEL YIP |
| Issued | 5/22/2025 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/6/2025 | ALEXANDER HELFER |
| Address approval | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/7/2025 | BRYAN GODINEZ |
| Sewer availability | Cleared | 5/7/2025 | BRYAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/23/2025 | Conditional Approval | RAUL OLAGI |
| BUILDING-Rough-Frame | 7/25/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 7/25/2025 | Approved | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/25/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 9/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 9/30/2025 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 9/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 9/30/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 11/4/2025 | Conditional Approval | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 11/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Rough | 11/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 11/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 11/14/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Drywall Nailing | 11/20/2025 | Approved | CHRISTOPHER ROJAS |