2506 S MANNING AVE 90064
Certificate Information: 2506 S MANNING AVE 90064
- Application / Permit
- 25016-10000-13705
- Plan Check / Job No.
- B25LA17158
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN.CONVERT EXISTING 2-CAR GARAGE & STORAGE SPACE TO AN ADU 718 S.F. PER LAMC 12.22 A.33(b)(1)3. NFPA 13D FIRE SPRINKLERS PROVIDED.
- Permit Issued
- Issued on 10/15/2025
- Issuing Office
- Current Status
- CofO Issued on 4/14/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/12/2025 | ALFREDO JARA |
| Corrections Issued | 5/13/2025 | ALFREDO JARA |
| Plan Check Approved | 8/5/2025 | ALFREDO JARA |
| Plan Check Approved | 10/10/2025 | ALFREDO JARA |
| Issued | 10/15/2025 | APPLICANT |
| CofO in Progress | 4/14/2026 | ASHLEY THOMPSON |
| Permit Finaled | 4/14/2026 | RICHARD STEINBACH |
| CofO Issued | 4/14/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/14/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/20/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/20/2025 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/20/2025 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/20/2025 | CARLOS AGUILERA |
| Specific Plan | Cleared | 6/24/2025 | HAMID GHAEMMAGHAMI |
| Construction near power lines | Cleared | 8/4/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/4/2025 | RIDWAN HARDY |
| Grading Pre-Inspection | Cleared | 8/5/2025 | ALFREDO JARA |
Contact Information
| Architect | , ; Lic. No.: C38799 | , |
| Contractor | Sharp Builders & Son; Lic. No.: 1144723-B | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2025 | Conditional Approval | DAVID FEILER |
| Footing/Foundation/Slab | 10/29/2025 | Corrections Issued | MICHAEL ALLEN |
| Deputy Wood Construction | 11/14/2025 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2025 | Partial Approval | EVAN COOPER |
| PLUMBING-Rough | 12/5/2025 | Partial Approval | ASHLEY THOMPSON |
| Sewer | 12/5/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 12/15/2025 | Approved | ASHLEY THOMPSON |
| METHANE-Rough | 12/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 12/22/2025 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 12/22/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/22/2025 | Partial Approval | ASHLEY THOMPSON |
| PLUMBING-Rough | 12/22/2025 | Approved | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/12/2026 | Approved | ANDREW NAVE |
| Insulation | 1/12/2026 | Approved | ANDREW NAVE |
| METHANE-Rough | 1/12/2026 | Approved | ANDREW NAVE |
| Drywall Nailing | 1/16/2026 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 2/23/2026 | Approved | ANDREW NAVE |
| Shower Pan | 2/23/2026 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 4/1/2026 | Approved | ASHLEY THOMPSON |
| Final | 4/1/2026 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 4/1/2026 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 4/1/2026 | Approved | ASHLEY THOMPSON |
| Final | 4/13/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 4/13/2026 | SGSOV Not Required | ASHLEY THOMPSON |
| Smoke Detectors | 4/13/2026 | Approved | ASHLEY THOMPSON |