5760 W 74TH ST 90045
Certificate Information: 5760 W 74TH ST 90045
- Application / Permit
- 25016-10000-13629
- Plan Check / Job No.
- B25LA17067
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel at 1st floor of single-family dwelling with removal of walls between dining and family room
- Permit Issued
- Issued on 5/14/2025
- Issuing Office
- Current Status
- Permit Finaled on 8/11/2025
Permit Application Status History
| Submitted | 4/30/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2025 | ALEC MOUSAKHANIAN |
| Corrections Issued | 5/3/2025 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 5/13/2025 | PINANK PATEL |
| Issued | 5/14/2025 | APPLICANT |
| Permit Finaled | 8/8/2025 | RUBEN RIVAS |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 5/6/2025 | LANNY MERRICK |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/25/2025 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 7/14/2025 | Corrections Issued | ANTHONY EGSON |
| MERV13>=Rough | 7/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Rough-Elec/Plmb/HVAC | 7/14/2025 | Not Ready for Inspection | ANTHONY EGSON |
| Insulation | 7/16/2025 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/21/2025 | Not Ready for Inspection | RUBEN RIVAS |
| MERV13>=Rough | 7/21/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Rough-Elec/Plmb/HVAC | 7/21/2025 | Not Ready for Inspection | RUBEN RIVAS |
| BUILDING-Rough-Frame | 7/22/2025 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 7/22/2025 | Approved | JESUS PINEDA |
| MERV13>=Rough | 7/22/2025 | Approved | JESUS PINEDA |
| Insulation | 7/25/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 7/29/2025 | Approved | BOBBY KEY |
| Special/Order Compliance | 7/29/2025 | Partial Inspection | TEMISTOCLES CAAL |
| Final | 8/8/2025 | Permit Finaled | RUBEN RIVAS |
| MERV13>=Final | 8/8/2025 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 8/8/2025 | SGSOV Approved | RUBEN RIVAS |
| Smoke Detectors | 8/8/2025 | Approved | RUBEN RIVAS |