13794 N MARCHANT AVE 91342

Certificate Information: 13794 N MARCHANT AVE 91342

Application / Permit
25016-10000-13491
Plan Check / Job No.
B25LA16917
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE TO STATE ACCESSORY DWELLING UNIT (ADU) PER GCS 66323(a)(1), ALL WORK PER WFPP
Permit Issued
Issued on 6/16/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/28/2025 APPLICANT
Assigned to Plan Check Engineer 5/2/2025 MINA HABILI
Corrections Issued 5/3/2025 MINA HABILI
Building Plans Picked Up 5/12/2025 APPLICANT
Plan Check Approved 6/12/2025 ZAW HAN
Issued 6/16/2025 APPLICANT
CofO in Progress 3/5/2026 KEVIN BERBERYAN
CofO Issued 4/2/2026 RUBEN SALAS
Permit Finaled 4/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/2/2025 MICHAEL BROWN
Sewer availability Cleared 6/2/2025 MICHAEL BROWN
Construction near power lines Cleared 6/3/2025 GEVORK KARAPETYAN
Eng Process Fee Ord 176,300 Cleared 6/3/2025 MICHAEL BROWN
Grading Pre-Inspection Cleared 6/10/2025 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/17/2025 Partial Inspection KEVIN BERBERYAN
PLUMBING-Rough 9/3/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 9/8/2025 Partial Approval MICHEL ABAJAN
Deputy Drilled-In Anchors 9/12/2025 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 9/12/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Rough 10/14/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 10/14/2025 Not Ready for Inspection KEVIN BERBERYAN
ELECTRICAL-Rough 10/17/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 10/17/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 10/29/2025 Approved KEVIN BERBERYAN
Green Building Rough 10/29/2025 Not Ready for Inspection KEVIN BERBERYAN
Interior/Exterior Lathing 10/31/2025 Partial Approval CHRISTOPHER MORFIN
HVAC-Rough 11/3/2025 Approved KEVIN BERBERYAN
Shower Pan 11/3/2025 Approved KEVIN BERBERYAN
Insulation 11/26/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 11/26/2025 Approved KEVIN BERBERYAN
Drywall Nailing 12/15/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 2/3/2026 Approved KEVIN BERBERYAN
Final 2/3/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/3/2026 Not Ready for Inspection KEVIN BERBERYAN
Green Building Rough 2/3/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/3/2026 SGSOV Not Ready KEVIN BERBERYAN
Smoke Detectors 2/3/2026 Approved KEVIN BERBERYAN
Final 2/18/2026 Corrections Issued KEVIN BERBERYAN
Green Building Final 2/18/2026 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 2/18/2026 SGSOV Approved KEVIN BERBERYAN
Final 2/24/2026 OK to Issue CofO KEVIN BERBERYAN