2333 S PATRICIA AVE 90064
Certificate Information: 2333 S PATRICIA AVE 90064
- Application / Permit
- 25016-10000-13313
- Plan Check / Job No.
- B25LA16746
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: CONVERT (E) GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1). WORK PER WFPP.
- Permit Issued
- Issued on 5/9/2025
- Issuing Office
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 5/1/2025 | DANIEL YIP |
| Corrections Issued | 5/1/2025 | DANIEL YIP |
| Plan Check Approved | 5/6/2025 | DANIEL YIP |
| Issued | 5/9/2025 | APPLICANT |
| CofO in Progress | 9/24/2025 | DANIEL VERA |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
| Permit Finaled | 9/25/2025 | RICHARD STEINBACH |
| CofO Issued | 9/25/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/2/2025 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2025 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 5/5/2025 | LANNY MERRICK |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Preferred Home Builders Inc; Lic. No.: 773147-B | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/16/2025 | Conditional Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 6/16/2025 | Corrections Issued | DANIEL VERA |
| Deputy Drilled-In Anchors | 7/3/2025 | Conditional Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 7/9/2025 | No Access for Inspection | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 7/11/2025 | Not Ready for Inspection | DANIEL VERA |
| Deputy Drilled-In Anchors | 7/17/2025 | Conditional Approval | DANIEL VERA |
| Excavation/Setback/Form/Re-Bar | 7/18/2025 | Approved | DANIEL VERA |
| Footing/Foundation/Slab | 7/18/2025 | Approved | DANIEL VERA |
| Underground Mechanical | 7/18/2025 | Approved | DANIEL VERA |
| Pre-Inspection | 7/29/2025 | Partial Approval | DANIEL VERA |
| BUILDING-Rough-Frame | 8/6/2025 | Not Ready for Inspection | DANIEL VERA |
| ELECTRICAL-Rough | 8/6/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Rough | 8/6/2025 | Corrections Issued | DANIEL VERA |
| PLUMBING-Rough | 8/6/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Rough | 8/8/2025 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2025 | Approved | DANIEL VERA |
| Gas Test | 8/8/2025 | Partial Approval | DANIEL VERA |
| HVAC-Rough | 8/8/2025 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 8/8/2025 | Not Ready for Inspection | DANIEL VERA |
| Shower Pan | 8/8/2025 | Approved | DANIEL VERA |
| Insulation | 8/12/2025 | Not Ready for Inspection | MICHAEL ALLEN |
| Interior/Exterior Lathing | 8/12/2025 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | DANIEL VERA |
| Green Building Rough | 8/15/2025 | Approved | DANIEL VERA |
| Insulation | 8/15/2025 | Approved | DANIEL VERA |
| Drywall Nailing | 8/18/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 9/18/2025 | Corrections Issued | DANIEL VERA |
| Final | 9/18/2025 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 9/18/2025 | Corrections Issued | DANIEL VERA |
| METHANE-Final | 9/18/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/18/2025 | Corrections Issued | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 9/18/2025 | Approved | DANIEL VERA |
| ELECTRICAL-Final | 9/22/2025 | Approved | DANIEL VERA |
| Final | 9/22/2025 | OK to Issue CofO | DANIEL VERA |
| HVAC-Final | 9/22/2025 | Approved | DANIEL VERA |
| PLUMBING-Final | 9/22/2025 | Approved | DANIEL VERA |