6328 S 8TH AVE 90043

Certificate Information: 6328 S 8TH AVE 90043

Application / Permit
25016-10000-13311
Plan Check / Job No.
B25LA16743
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETAHCED GARAGE TO ACCESSORY DWELLING UNIT PER GC 66323(a)(1).
Permit Issued
Issued on 5/19/2025
Issuing Office
Current Status
CofO Issued on 9/18/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2025 APPLICANT
Assigned to Plan Check Engineer 4/30/2025 ROSENDO MEDINA
Corrections Issued 4/30/2025 ROSENDO MEDINA
Plan Check Approved 5/13/2025 ROSENDO MEDINA
Issued 5/19/2025 APPLICANT
CofO in Progress 9/16/2025 MICHAEL LEWIS
Permit Finaled 9/18/2025 DEROLD HAUFF
CofO Issued 9/18/2025 DEROLD HAUFF
Permit Finaled 9/18/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/1/2025 ABEL CASILLAS
Sewer availability Cleared 5/1/2025 ABEL CASILLAS
Eng Process Fee Ord 176,300 Cleared 5/9/2025 ABEL CASILLAS

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/5/2025 Approved WAYNE REGESTER
Footing/Foundation/Slab 6/9/2025 Approved WAYNE REGESTER
Deputy Drilled-In Anchors 6/10/2025 Conditional Approval ANTHONY RAMOS
ELECTRICAL-Rough 6/23/2025 Partial Approval LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved LUIS CASTRO
PLUMBING-Rough 6/23/2025 Approved LUIS CASTRO
Sewer 6/23/2025 Approved LUIS CASTRO
Underground Mechanical 6/23/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 6/27/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Rough 6/27/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Rough 6/27/2025 Not Ready for Inspection WAYNE REGESTER
Shower Pan 6/27/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 7/3/2025 Approved WAYNE REGESTER
Green Building Rough 7/3/2025 Approved WAYNE REGESTER
HVAC-Rough 7/3/2025 Approved WAYNE REGESTER
Interior/Exterior Lathing 7/3/2025 Approved WAYNE REGESTER
Shower Pan 7/3/2025 Approved WAYNE REGESTER
Insulation 7/9/2025 Approved WAYNE REGESTER
Drywall Nailing 7/14/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
Final 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
Green Building Final 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
HVAC-Final 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
PLUMBING-Final 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 9/5/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 9/5/2025 No Access for Inspection SALVADOR MARTINEZ
ELECTRICAL-Final 9/9/2025 Corrections Issued SALVADOR MARTINEZ
Final 9/9/2025 Corrections Issued SALVADOR MARTINEZ
Green Building Final 9/9/2025 Approved SALVADOR MARTINEZ
HVAC-Final 9/9/2025 Approved SALVADOR MARTINEZ
PLUMBING-Final 9/9/2025 Corrections Issued SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 9/9/2025 SGSOV Not Ready SALVADOR MARTINEZ
Smoke Detectors 9/9/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 9/15/2025 Approved MICHAEL LEWIS
Final 9/15/2025 OK to Issue CofO MICHAEL LEWIS
HVAC-Final 9/15/2025 Approved MICHAEL LEWIS
PLUMBING-Final 9/15/2025 Approved MICHAEL LEWIS
SGSOV-Seismic Gas S/O Valve 9/15/2025 SGSOV Approved MICHAEL LEWIS