5173 S VAN NESS AVE 90062

Certificate Information: 5173 S VAN NESS AVE 90062

Application / Permit
25016-10000-13161
Plan Check / Job No.
B25LA16502
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GC 66323(a)(4).
Permit Issued
Issued on 9/29/2025
Issuing Office
Current Status
CofO Issued on 4/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2025 APPLICANT
Assigned to Plan Check Engineer 5/7/2025 ROSENDO MEDINA
Corrections Issued 5/8/2025 ROSENDO MEDINA
Applicant returned to address corrections 7/23/2025 ROSENDO MEDINA
Applicant returned to address corrections 8/7/2025 MOHAMMAD ESMAILI
Applicant returned to address corrections 8/15/2025 ROSENDO MEDINA
Applicant returned to address corrections 8/27/2025 ROSENDO MEDINA
Plan Check Approved 9/2/2025 ROSENDO MEDINA
Issued 9/29/2025 APPLICANT
CofO in Progress 4/8/2026 LUIS CASTRO
No Progress 4/9/2026 DEROLD HAUFF
CofO in Progress 4/9/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF
CofO Issued 4/13/2026 DEROLD HAUFF
Permit Finaled 4/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/9/2025 MICHAEL BROWN
Sewer availability Cleared 6/9/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 6/11/2025 MICHAEL BROWN
Tenant Habitability Plan Cleared 8/4/2025 ARIC DEFUSCO

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22814 DOLOROSA ST      WOODLAND HILLS, CA 91367

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/24/2025 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 11/25/2025 Corrections Issued LUIS CASTRO
Footing/Foundation/Slab 12/15/2025 Approved LUIS CASTRO
PLUMBING-Rough 12/15/2025 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 1/13/2026 Not Ready for Inspection LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 1/13/2026 Corrections Issued LUIS CASTRO
Green Building Rough 1/13/2026 Not Ready for Inspection LUIS CASTRO
PLUMBING-Rough 1/13/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/3/2026 Partial Approval LUIS CASTRO
ELECTRICAL-Rough 2/3/2026 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/3/2026 Approved LUIS CASTRO
HVAC-Rough 2/3/2026 Approved LUIS CASTRO
BUILDING-Rough-Frame 2/13/2026 Approved LUIS CASTRO
Floor/Roof Diaphrgm/Shear Wall 2/13/2026 Approved LUIS CASTRO
Green Building Rough 2/13/2026 Approved LUIS CASTRO
Interior/Exterior Lathing 2/13/2026 Partial Approval LUIS CASTRO
Sewer 2/13/2026 Approved LUIS CASTRO
Underground Mechanical 2/13/2026 Approved LUIS CASTRO
Insulation 2/19/2026 Approved MICHAEL LEWIS
Shower Pan 2/19/2026 Approved MICHAEL LEWIS
Drywall Nailing 2/27/2026 Approved ALEX COLIN
Interior/Exterior Lathing 2/27/2026 Approved ALEX COLIN
ELECTRICAL-Final 4/7/2026 Approved LUIS CASTRO
Final 4/7/2026 OK to Issue CofO LUIS CASTRO
Green Building Final 4/7/2026 Approved LUIS CASTRO
HVAC-Final 4/7/2026 Approved LUIS CASTRO
PLUMBING-Final 4/7/2026 Approved LUIS CASTRO
SGSOV-Seismic Gas S/O Valve 4/7/2026 SGSOV Not Required LUIS CASTRO
Service/Power Release 4/7/2026 Approved LUIS CASTRO
Smoke Detectors 4/7/2026 Approved LUIS CASTRO