555 S FLOWER ST 48th Floor 90071

Certificate Information: 555 S FLOWER ST 48th Floor 90071

Application / Permit
25016-10000-12976
Plan Check / Job No.
B25LA16277
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Office
Work Description
EPLAN: TENANT IMPROVEMENT FOR STRUCTURAL REINFORCEMENT ON 48TH FLOOR FOR HIGH DENSITY FILING SYTEM OF (E) OFFICE
Permit Issued
Issued on 10/22/2025
Issuing Office
Current Status
Issued on 10/22/2025

Permit Application Status History

Submitted 4/29/2025 APPLICANT
Assigned to Plan Check Engineer 5/2/2025 GURUNATH NESARAJAH
Corrections Issued 5/5/2025 GURUNATH NESARAJAH
Plan Check Approved 5/16/2025 FELIX FIGUEROA
Issued 10/22/2025 APPLICANT

Permit Application Clearance Information

"D" conditions Cleared 5/12/2025 ROSALINDA MEZA
Community Plan Implem. Overlay Cleared 5/12/2025 ROSALINDA MEZA
Miscellaneous Cleared 5/12/2025 ROSALINDA MEZA
Miscellaneous Cleared 5/12/2025 ROSALINDA MEZA

Contact Information

Architect Mccaul,, Patricia A; Lic. No.: C26315 4150 IRVING PLACE      CULVER CITY, CA 90232
Contractor Howard Building Corporation; Lic. No.: 445804-B       ,
Engineer Wilkerson,, Ryan Lee; Lic. No.: NA4728       ,

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Final 7/28/2026   

Inspection Request History

Deputy Fireproofing 4/21/2026 Partial Approval PAUL BAZERKANIAN
Deputy Steel/Welding 4/21/2026 Partial Approval PAUL BAZERKANIAN
Final 4/21/2026 Not Ready for Inspection PAUL BAZERKANIAN
SGSOV-Seismic Gas S/O Valve 4/21/2026 SGSOV Approved PAUL BAZERKANIAN
Smoke Detectors 4/21/2026 Approved PAUL BAZERKANIAN
Deputy Fireproofing 4/22/2026 Partial Approval PAUL BAZERKANIAN
Deputy Steel/Welding 4/22/2026 Partial Approval PAUL BAZERKANIAN