3870 W UDELL CT 90027
Certificate Information: 3870 W UDELL CT 90027
- Application / Permit
- 25016-10000-12870
- Plan Check / Job No.
- B25LA16096
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan. Convert (e) attached 1-car garage to livable space and remove parking per AB 2097
- Permit Issued
- Issued on 6/11/2025
- Issuing Office
- Current Status
- CofO Issued on 10/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/23/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | REZA HAGHIGHAT |
| Corrections Issued | 4/26/2025 | REZA HAGHIGHAT |
| Plan Check Approved | 6/7/2025 | REZA HAGHIGHAT |
| Issued | 6/11/2025 | APPLICANT |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
| CofO Issued | 10/11/2025 | DEROLD HAUFF |
| Permit Finaled | 10/11/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/2/2025 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 5/2/2025 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2025 | SAFA JAVANMARDI |
| Hydrant and Access approval | Cleared | 5/27/2025 | FRANK GOMEZ |
| Grading Pre-Inspection | Cleared | 6/7/2025 | REZA HAGHIGHAT |
Contact Information
| Contractor | Oakasa Construction Services; Lic. No.: 1098151-B | , |
| Contractor | Oakasa Inc; Lic. No.: 1098151-B | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: NA76761 | , |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/3/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 7/3/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/9/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/10/2025 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/16/2025 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 7/17/2025 | Conditional Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 7/22/2025 | Approved | JOSE MACIAS |
| Deputy Drilled-In Anchors | 7/31/2025 | Conditional Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 8/6/2025 | Partial Approval | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 8/12/2025 | Corrections Issued | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/15/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 8/15/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 8/15/2025 | Conditional Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/19/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 8/28/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 8/28/2025 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 8/28/2025 | Partial Approval | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/3/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 9/3/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/3/2025 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 9/9/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 9/9/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/30/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/30/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/30/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 9/30/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/30/2025 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/30/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/3/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 10/3/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 10/3/2025 | Approved | ENRIQUE MIRELES |
| Final | 10/7/2025 | Conditional Approval | ENRIQUE MIRELES |