3014 N TYBURN ST 90039
Certificate Information: 3014 N TYBURN ST 90039
- Application / Permit
- 25016-10000-12569
- Plan Check / Job No.
- B25LA15827
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT PORTION OF (E) DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A). ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 10/6/2025
- Issuing Office
- Current Status
- CofO Issued on 2/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/28/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 5/14/2025 | PINANK PATEL |
| Applicant returned to address corrections | 9/3/2025 | MIROOSH KHACHATOORIAN |
| Applicant returned to address corrections | 9/16/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 10/6/2025 | GURUNATH NESARAJAH |
| Issued | 10/6/2025 | APPLICANT |
| CofO in Progress | 2/11/2026 | CHARLES BOGHOSKHAN |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
| CofO Issued | 2/13/2026 | DEROLD HAUFF |
| Permit Finaled | 2/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/15/2025 | MICHAEL BROWN |
| Sewer availability | Cleared | 5/15/2025 | MICHAEL BROWN |
| Eng Process Fee Ord 176,300 | Cleared | 5/19/2025 | MICHAEL BROWN |
| Construction near power lines | Cleared | 8/28/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 8/28/2025 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| NICHOLAS LOPEZ, (213) 202-3224 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/9/2025 | Approved | NICHOLAS LOPEZ |
| Footing/Foundation/Slab | 10/9/2025 | Conditional Approval | NICHOLAS LOPEZ |
| PLUMBING-Rough | 10/9/2025 | Partial Approval | NICHOLAS LOPEZ |
| Rough-Elec/Plmb/HVAC | 10/23/2025 | Corrections Issued | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/27/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Rough | 10/27/2025 | Approved | NICHOLAS LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2025 | Partial Approval | NICHOLAS LOPEZ |
| HVAC-Rough | 10/27/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Rough | 10/27/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 11/10/2025 | Corrections Issued | GEM DE OCAMPO |
| Drywall Nailing | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Green Building Rough | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Insulation | 11/14/2025 | Approved | NICHOLAS LOPEZ |
| Interior/Exterior Lathing | 12/5/2025 | Approved | GEM DE OCAMPO |
| Shower Pan | 12/5/2025 | Approved | GEM DE OCAMPO |
| Final | 2/3/2026 | Corrections Issued | NICHOLAS LOPEZ |
| Green Building Final | 2/3/2026 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 2/3/2026 | SGSOV Approved | NICHOLAS LOPEZ |
| Smoke Detectors | 2/3/2026 | Approved | NICHOLAS LOPEZ |
| Final | 2/10/2026 | OK to Issue CofO | NICHOLAS LOPEZ |