4326-4326 1/2 E YORK BLVD 90041
Certificate Information: 4326-4326 1/2 E YORK BLVD 90041
- Application / Permit
- 25016-10000-12253
- Plan Check / Job No.
- B25LA15472
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 13'-4" X 27'-10" PORTION OF UNDERFLOOR SPACE INTO A.D.U. PER STATE LAW (GCS 66323(a)(1)) COMPLY WITH DEPARTMENT ORDER effective date 05/31/2023. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE *see comments*
- Permit Issued
- Issued on 6/6/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/18/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2025 | LAWRENCE QUIRANTE |
| Corrections Issued | 4/24/2025 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/25/2025 | APPLICANT |
| Applicant returned to address corrections | 5/9/2025 | SUNMIN LEE |
| Applicant returned to address corrections | 5/16/2025 | RICARDO RAMIREZ |
| Plan Check Approved | 6/6/2025 | JOHN MESIAS |
| Issued | 6/6/2025 | APPLICANT |
| CofO in Progress | 10/8/2025 | JACOB SEGURA |
| Permit Finaled | 1/13/2026 | DANIEL SANCHEZ |
| CofO Issued | 1/13/2026 | DANIEL SANCHEZ |
| Permit Finaled | 1/13/2026 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2025 | DAVID LOPEZ |
| Sewer availability | Cleared | 4/24/2025 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2025 | ABEL CASILLAS |
| Supp. Use District POD/CDO/TDO | Cleared | 4/25/2025 | ANDREA MAGANA-WITHERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21731 VENTURA BLVD SUITE 110 WOODLAND HILLS, CA 91364 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/12/2025 | Corrections Issued | JACOB SEGURA |
| BUILDING-Rough-Frame | 6/25/2025 | Corrections Issued | JACOB SEGURA |
| ELECTRICAL-Rough | 6/25/2025 | Corrections Issued | JACOB SEGURA |
| Footing/Foundation/Slab | 6/25/2025 | Partial Approval | JACOB SEGURA |
| PLUMBING-Rough | 6/25/2025 | Corrections Issued | JACOB SEGURA |
| Sewer | 6/25/2025 | Not Ready for Inspection | JACOB SEGURA |
| ELECTRICAL-Final | 7/3/2025 | Conditional Approval | FERMIN RUBIO |
| PLUMBING-Rough | 7/3/2025 | Not Ready for Inspection | FERMIN RUBIO |
| PLUMBING-Final | 7/11/2025 | Conditional Approval | FERMIN RUBIO |
| Wood Frame | 7/11/2025 | Conditional Approval | FERMIN RUBIO |
| BUILDING-Rough-Frame | 7/17/2025 | Corrections Issued | JACOB SEGURA |
| Green Building Rough | 7/17/2025 | Not Ready for Inspection | JACOB SEGURA |
| BUILDING-Rough-Frame | 9/4/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Rough | 9/4/2025 | Approved | JACOB SEGURA |
| Footing/Foundation/Slab | 9/4/2025 | Approved | JACOB SEGURA |
| Green Building Rough | 9/4/2025 | Approved | JACOB SEGURA |
| HVAC-Rough | 9/4/2025 | Corrections Issued | JACOB SEGURA |
| Insulation | 9/4/2025 | Approved | JACOB SEGURA |
| Interior/Exterior Lathing | 9/4/2025 | Approved | JACOB SEGURA |
| PLUMBING-Rough | 9/4/2025 | Approved | JACOB SEGURA |
| Shower Pan | 9/4/2025 | Approved | JACOB SEGURA |
| Final | 9/25/2025 | Corrections Issued | JACOB SEGURA |
| Green Building Final | 9/25/2025 | Not Ready for Inspection | JACOB SEGURA |
| Smoke Detectors | 9/25/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Final | 10/7/2025 | Approved | JACOB SEGURA |
| Final | 10/7/2025 | OK to Issue CofO | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2025 | Approved | JACOB SEGURA |
| Green Building Final | 10/7/2025 | Approved | JACOB SEGURA |
| HVAC-Final | 10/7/2025 | Approved | JACOB SEGURA |
| HVAC-Rough | 10/7/2025 | Approved | JACOB SEGURA |
| PLUMBING-Final | 10/7/2025 | Approved | JACOB SEGURA |
| Sewer | 10/7/2025 | Approved | JACOB SEGURA |