5666-5668 E RABER ST 90042
Certificate Information: 5666-5668 E RABER ST 90042
- Application / Permit
- 25016-10000-12064
- Plan Check / Job No.
- B25LA15264
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- eplan CONVERT (E) ATTACHED STORAGE ON FIRST FLOOR OF (E) 2-STORY SFD TO AN ATTACHED ACCESSORY DWELLING UNIT PER GC 66323(a)(1)
- Permit Issued
- Issued on 7/9/2025
- Issuing Office
- Current Status
- CofO Issued on 3/26/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/17/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2025 | KAMYAR EMAMI |
| Corrections Issued | 4/23/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 5/10/2025 | KAMYAR EMAMI |
| Plan Check Approved | 5/21/2025 | SAMUEL GONZALEZ |
| Issued | 7/9/2025 | APPLICANT |
| CofO in Progress | 3/25/2026 | DAVID WILLIAMS |
| CofO Issued | 3/26/2026 | DEROLD HAUFF |
| Permit Finaled | 3/26/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/24/2025 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 4/24/2025 | LEE GUILBEAUX |
| Sewer availability | Cleared | 4/24/2025 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 4/24/2025 | LEE GUILBEAUX |
Contact Information
| Architect | Kivotos,, Juan M; Lic. No.: NA26491 | , |
| Contractor | Ibarra'S Construction; Lic. No.: 980320-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 7/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| PLUMBING-Rough | 7/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| Pre-Inspection | 7/30/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 7/30/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| ELECTRICAL-Rough | 10/16/2025 | Approved | DAVID WILLIAMS |
| Wood Frame | 10/16/2025 | Not Ready for Inspection | DAVID WILLIAMS |
| BUILDING-Rough-Frame | 11/25/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Rough | 11/25/2025 | Approved | DAVID WILLIAMS |
| Insulation | 11/26/2025 | Approved | DAVID WILLIAMS |
| Drywall Nailing | 12/2/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 3/11/2026 | Approved | DAVID WILLIAMS |
| Final | 3/11/2026 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Final | 3/11/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 3/11/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 3/11/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 3/11/2026 | Approved | DAVID WILLIAMS |
| Final | 3/25/2026 | OK to Issue CofO | DAVID WILLIAMS |