12931 W LA MAIDA ST 91423

Certificate Information: 12931 W LA MAIDA ST 91423

Application / Permit
25016-10000-12032
Plan Check / Job No.
B25LA15219
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE AND RECREATION ROOM TO ACCESSORY DWELLING UNIT PER GCS 66323(a)(1).
Permit Issued
Issued on 5/15/2025
Issuing Office
Current Status
CofO Issued on 6/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2025 APPLICANT
Assigned to Plan Check Engineer 4/22/2025 MADISON ODELL
Corrections Issued 4/23/2025 MADISON ODELL
Applicant returned to address corrections 5/2/2025 MADISON ODELL
Plan Check Approved 5/8/2025 GURUNATH NESARAJAH
Issued 5/15/2025 APPLICANT
CofO in Progress 6/3/2026 RAUL OLAGI
CofO Issued 6/9/2026 RUBEN SALAS
Permit Finaled 6/9/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/28/2025 MICHAEL BROWN
Eng Process Fee Ord 176,300 Cleared 4/29/2025 MICHAEL BROWN
Sewer availability Cleared 4/29/2025 MICHAEL BROWN

Contact Information

Contractor Better Together Builders Inc; Lic. No.: 1047689-B       ,
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Sewer 7/11/2025 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 7/17/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 7/17/2025 Partial Approval GAREN HAYRAPETYAN
Underground Mechanical 7/23/2025 Partial Approval OGANES TARAKHCHYAN
Gas Test 7/29/2025 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 8/13/2025 Approved OGANES TARAKHCHYAN
HVAC-Rough 8/13/2025 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 8/13/2025 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Rough 9/10/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/10/2025 Not Ready for Inspection OGANES TARAKHCHYAN
MERV13>=Rough 9/10/2025 Approved OGANES TARAKHCHYAN
Shower Pan 9/10/2025 Corrections Issued OGANES TARAKHCHYAN
BUILDING-Rough-Frame 9/15/2025 Approved OGANES TARAKHCHYAN
Insulation 9/15/2025 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/15/2025 Approved OGANES TARAKHCHYAN
Shower Pan 9/15/2025 Approved OGANES TARAKHCHYAN
Drywall Nailing 9/19/2025 Approved WAYNE REGESTER
ELECTRICAL-Final 12/9/2025 Not Ready for Inspection WAYNE REGESTER
Final 12/9/2025 Not Ready for Inspection WAYNE REGESTER
Green Building Final 12/9/2025 Not Ready for Inspection WAYNE REGESTER
HVAC-Final 12/9/2025 Not Ready for Inspection WAYNE REGESTER
MERV13>=Final 12/9/2025 Not Ready for Inspection WAYNE REGESTER
PLUMBING-Final 12/9/2025 Approved WAYNE REGESTER
SGSOV-Seismic Gas S/O Valve 12/9/2025 SGSOV Approved WAYNE REGESTER
Smoke Detectors 12/9/2025 Not Ready for Inspection WAYNE REGESTER
Final 12/18/2025 Corrections Issued JOSE AVILA
Final 1/13/2026 Not Ready for Inspection WAYNE REGESTER
Green Building Final 1/13/2026 Approved WAYNE REGESTER
MERV13>=Final 1/13/2026 Approved WAYNE REGESTER
Smoke Detectors 1/13/2026 Approved WAYNE REGESTER
Final 2/25/2026 Partial Approval WAYNE REGESTER
Final 3/2/2026 Corrections Issued MICHAEL CORTEZ
Final 6/2/2026 OK to Issue CofO RAUL OLAGI