3587 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3587 S MOUNTAIN VIEW AVE 90066

Application / Permit
25016-10000-11770
Plan Check / Job No.
B25LA14915
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
EPLAN PROPOSED INTERIOR REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING. 1 OF 2
Permit Issued
Issued on 12/17/2025
Issuing Office
Current Status
Issued on 12/17/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/15/2025 APPLICANT
Assigned to Plan Check Engineer 4/17/2025 MICHAEL LOPEZ
Corrections Issued 4/28/2025 MICHAEL LOPEZ
Quality Review Completed 5/6/2025 PRANITA SHAH
Applicant returned to address corrections 8/1/2025 MICHAEL LOPEZ
Applicant returned to address corrections 8/29/2025 MICHAEL LOPEZ
Applicant returned to address corrections 11/14/2025 MICHAEL LOPEZ
Plan Check Approved 12/16/2025 MICHAEL LOPEZ
Issued 12/17/2025 APPLICANT

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/17/2025 LANNY MERRICK
Sewer availability Cleared 7/3/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 7/16/2025 COLIN LOREDO
Roof/Waste drainage to street Cleared 9/12/2025 CARLOS AGUILERA
Specific Plan Cleared 10/9/2025 EDER ROMERO
GPI Written Notices Cleared 11/20/2025 MICHAEL LOPEZ

Contact Information

Architect Chan,, John K; Lic. No.: NA35342       ,
Contractor Build Zone Corp; Lic. No.: 1098273-B       ,
Engineer Garza,, Omar Leonel; Lic. No.: S5593 5050 EAGLE ROCK BOULEVARD      LOS ANGELES, CA 90041

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/10/2026 Corrections Issued MICHAEL ALLEN
Footing/Foundation/Slab 2/19/2026 Partial Approval CARLOS MATAMOROS
Deputy Reinf. Concrete 3/11/2026 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 3/11/2026 Conditional Approval ANDREW NAVE
Deputy Drilled-In Anchors 3/31/2026 Conditional Approval ANDREW NAVE
Deputy Reinf. Concrete 3/31/2026 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 4/6/2026 Approved RUBEN RIVAS
Green Building Rough 4/6/2026 Not Ready for Inspection RUBEN RIVAS
Footing/Foundation/Slab 4/10/2026 Approved RYAN SALAZAR
Light Gage Steel Frame 4/10/2026 Not Ready for Inspection RYAN SALAZAR
PLUMBING-Rough 4/10/2026 Partial Approval RYAN SALAZAR
Structural Steel Frame 4/10/2026 Not Ready for Inspection RYAN SALAZAR
Deputy Drilled-In Anchors 4/15/2026 Conditional Approval ANDREW NAVE
Deputy Wood Construction 4/15/2026 Conditional Approval ANDREW NAVE
PLUMBING-Rough 4/17/2026 Approved RYAN SALAZAR
BUILDING-Rough-Frame 4/23/2026 Partial Approval EUGENE CASSIDY
Green Building Rough 4/23/2026 Not Ready for Inspection EUGENE CASSIDY
HVAC-Rough 4/30/2026 Corrections Issued ANTHONY EGSON
Deputy Reinf. Concrete 5/7/2026 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 5/7/2026 Conditional Approval ANDREW NAVE