8500 W BEVERLY BLVD 656 90048
Certificate Information: 8500 W BEVERLY BLVD 656 90048
- Application / Permit
- 25016-10000-11600
- Plan Check / Job No.
- B25LA14726
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Eplan Change of use from retail (5368 sf. )to game of skill and science (escape room), within existing covered mall. Work to include new interior non-structural partition walls, new interior finishes, and new millwork. Existing storefront to remain. No change in parking, utilize AB 2097.
- Permit Issued
- Issued on 7/22/2025
- Issuing Office
- Current Status
- CofO Issued on 1/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/17/2025 | SAM CHANG |
| Corrections Issued | 5/13/2025 | SAM CHANG |
| Quality Review Completed | 5/14/2025 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/11/2025 | SAM CHANG |
| Plan Check Approved | 7/22/2025 | SAM CHANG |
| Issued | 7/22/2025 | APPLICANT |
| CofO in Progress | 1/9/2026 | MARTIN TAVITIAN |
| Permit Finaled | 1/13/2026 | ERNESTO CORRAL |
| CofO Issued | 1/13/2026 | ERNESTO CORRAL |
| Permit Finaled | 1/13/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 5/23/2025 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/27/2025 | CARLOS AGUILERA |
| ZA Case | Cleared | 6/24/2025 | EDWIN CANO |
| ZA Case | Cleared | 6/24/2025 | EDWIN CANO |
| Fire Marshal Fire Life Safety | Cleared | 7/3/2025 | FIRE DEPARTMENT |
| DAS Clearance | Cleared | 7/16/2025 | ELIZABETH TOMS |
Contact Information
| Architect | Calnon,, Robert Andrew; Lic. No.: NA26387 | , |
| Contractor | Dumonde Builders Inc; Lic. No.: 1097290-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 7/24/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/15/2025 | Conditional Approval | MARTIN TAVITIAN |
| Drywall Nailing | 8/25/2025 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 8/25/2025 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 8/29/2025 | Approved | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 9/5/2025 | Partial Approval | MARTIN TAVITIAN |
| Light Gage Steel Frame | 9/16/2025 | Approved | MARTIN TAVITIAN |
| T-Bar Ceiling | 9/16/2025 | Approved | MARTIN TAVITIAN |
| T-Bar Ceiling | 9/18/2025 | Approved | MARTIN TAVITIAN |
| Final | 10/3/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| METHANE-Final | 10/3/2025 | Approved | MARTIN TAVITIAN |
| METHANE-Rough | 10/3/2025 | Approved | MARTIN TAVITIAN |
| Reinforced Concrete Frame | 10/3/2025 | Approved | MARTIN TAVITIAN |
| SGSOV-Seismic Gas S/O Valve | 10/3/2025 | SGSOV Approved | MARTIN TAVITIAN |
| Smoke Detectors | 10/3/2025 | Conditional Approval | MARTIN TAVITIAN |
| Final | 12/30/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Smoke Detectors | 12/30/2025 | Approved | MARTIN TAVITIAN |
| Final | 1/7/2026 | OK to Issue CofO | MARTIN TAVITIAN |