400 S HOPE ST 1100 90071
Certificate Information: 400 S HOPE ST 1100 90071
- Application / Permit
- 25016-10000-11369
- Plan Check / Job No.
- B25LA14426
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Eplan. Tenant improvements in existing building: include demolishing of non-structural partitions and building new non-structural partitions, new lighting, power & finishes.
- Permit Issued
- Issued on 5/13/2025
- Issuing Office
- Current Status
- Permit Finaled on 7/22/2025
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2025 | KAVIAN REFAHI |
| Plan Check Approved | 4/13/2025 | KAVIAN REFAHI |
| Issued | 5/13/2025 | APPLICANT |
| Permit Finaled | 7/22/2025 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Lebrilla,, Ariane; Lic. No.: C38312 | 1126 STANYAN ST APT #2 SAN FRANCISCO, CA 94117 |
| Architect | Lebrilla,, Ariane; Lic. No.: NA38312 | , |
| Contractor | Howard Building Corporation; Lic. No.: 445804-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/18/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 6/23/2025 | Partial Approval | PAUL BAZERKANIAN |
| Insulation | 6/23/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 6/25/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 7/14/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 7/22/2025 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 7/22/2025 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 7/22/2025 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 7/22/2025 | Approved | PAUL BAZERKANIAN |