400 S HOPE ST 900 90071
Certificate Information: 400 S HOPE ST 900 90071
- Application / Permit
- 25016-10000-11367
- Plan Check / Job No.
- B25LA14422
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- Eplan. Tenant improvements in existing office space. Work includes demolishing of non-structural partitions and building new non-structural partitions, new paint and flooring throughout suite.
- Permit Issued
- Issued on 5/20/2025
- Issuing Office
- Current Status
- Permit Finaled on 1/22/2026
Permit Application Status History
| Submitted | 4/11/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2025 | ADAM HEGAZI |
| Corrections Issued | 4/12/2025 | ADAM HEGAZI |
| Plan Check Approved | 4/20/2025 | CARLOS MONTES |
| Issued | 5/20/2025 | APPLICANT |
| Permit Finaled | 1/22/2026 | PAUL BAZERKANIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Lebrilla,, Ariane; Lic. No.: NA38312 | , |
| Contractor | Corporate Contractors Inc; Lic. No.: 604407-B | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 6/25/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 6/27/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 7/21/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 7/21/2025 | Partial Approval | PAUL BAZERKANIAN |
| Drywall Nailing | 7/22/2025 | Not Ready for Inspection | PAUL BAZERKANIAN |
| Drywall Nailing | 7/23/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 8/15/2025 | Partial Approval | JEROME BLACKWOOD |
| Drywall Nailing | 8/27/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 9/29/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 1/22/2026 | Permit Finaled | PAUL BAZERKANIAN |
| Green Building Final | 1/22/2026 | Approved | PAUL BAZERKANIAN |
| SGSOV-Seismic Gas S/O Valve | 1/22/2026 | SGSOV Approved | PAUL BAZERKANIAN |
| Smoke Detectors | 1/22/2026 | Approved | PAUL BAZERKANIAN |