3388 S ROBERTSON BLVD 90034

Certificate Information: 3388 S ROBERTSON BLVD 90034

Application / Permit
25016-10000-11324
Plan Check / Job No.
B25LA14332
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(21) Adult Cabaret
Work Description
FIRE DAMAGE REPAIR AND REPLACE ROOF FRAMING WITH NEW TRUSSES . AND NEW ROOF MOUNTED EQUIPMENT PLATFORMS . "COMPLY WITH DEPARTMENT ORDER effective date 12/27/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE". CEIS Case #1032344.
Permit Issued
Issued on 5/30/2025
Issuing Office
Current Status
Permit Finaled on 3/3/2026

Permit Application Status History

Submitted 4/11/2025 APPLICANT
Assigned to Plan Check Engineer 4/16/2025 DANIEL SANJUAN
Corrections Issued 4/17/2025 DANIEL SANJUAN
Building Plans Picked Up 4/21/2025 APPLICANT
Plan Check Approved 5/27/2025 GEORGE ALVAREZ
Issued 5/30/2025 APPLICANT
Permit Finaled 3/3/2026 FARHAD DADBIN

Permit Application Clearance Information

Specific Plan Cleared 5/5/2025 JULISSA LOPEZ-HODOYAN

Contact Information

Contractor Master Home Design & Builders Inc; Lic. No.: 1096721-B 22647 VENTURA BLVD   SUITE 726    WOODLAND HILLS, CA 91364
Engineer Ortiz,, Roberto; Lic. No.: S5512 1744 W KATELLA AVE STE 107      ORANGE, CA 92867
Engineer Reinmuth,, Dustin; Lic. No.: C91547 12305 FESTIVAL LANE      NORTHGLENN, CO 80241

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Wood Frame 7/28/2025 Not Ready for Inspection FARHAD DADBIN
Wood Frame 10/22/2025 Approved VASIL MIHALEV
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Approved FARHAD DADBIN
Insulation 10/30/2025 Approved FARHAD DADBIN
Final 10/31/2025 Corrections Issued FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 10/31/2025 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 10/31/2025 Not Ready for Inspection FARHAD DADBIN
Drywall Nailing 11/6/2025 Partial Approval FARHAD DADBIN
Interior/Exterior Lathing 11/6/2025 Approved FARHAD DADBIN
Drywall Nailing 11/10/2025 Approved FARHAD DADBIN
Final 3/3/2026 Permit Finaled FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 3/3/2026 SGSOV Approved FARHAD DADBIN