10726 W AYRES AVE 90064
Certificate Information: 10726 W AYRES AVE 90064
- Application / Permit
- 25016-10000-11031
- Plan Check / Job No.
- B25LA13958
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL OF ENTIRE (E) SINGLE FAMILY DWELLING. RE-FRAME ROOF. ALL WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 8/12/2025
- Issuing Office
- Current Status
- Permit Finaled on 4/21/2026
Permit Application Status History
| Submitted | 4/14/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2025 | KAMYAR EMAMI |
| Corrections Issued | 4/21/2025 | KAMYAR EMAMI |
| Applicant returned to address corrections | 6/11/2025 | MADISON ODELL |
| Plan Check Approved | 6/26/2025 | KAMYAR EMAMI |
| Issued | 8/12/2025 | APPLICANT |
| Permit Finaled | 4/21/2026 | EVAN COOPER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/23/2025 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2025 | LIAM ODONOVAN |
| Sewer availability | Cleared | 4/28/2025 | LIAM ODONOVAN |
| Flood clearance | Cleared | 6/5/2025 | ELYSE GREPO |
Contact Information
| Architect | Gormally,, Vincent E; Lic. No.: C27133 | , |
| Contractor | Green Works Construction & Design Inc; Lic. No.: 936962-B | , |
| Engineer | Perazzelli,, Joseph Ames; Lic. No.: NA35270 | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/17/2025 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 11/4/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 11/25/2025 | Partial Approval | KIRK SANDERS |
| ELECTRICAL-Rough | 11/25/2025 | Corrections Issued | KIRK SANDERS |
| HVAC-Rough | 11/25/2025 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Rough | 11/25/2025 | Approved | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/15/2026 | Conditional Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 1/15/2026 | Partial Approval | KIRK SANDERS |
| Special/Order Compliance | 1/15/2026 | Corrections Issued | KIRK SANDERS |
| BUILDING-Rough-Frame | 1/21/2026 | Approved | DANIEL VERA |
| Insulation | 1/21/2026 | Approved | DANIEL VERA |
| Drywall Nailing | 1/29/2026 | Approved | MICHAEL ALLEN |
| Shower Pan | 1/29/2026 | Approved | MICHAEL ALLEN |
| Shower Pan | 2/2/2026 | Partial Inspection | WILBER ROSALES |
| Interior/Exterior Lathing | 2/4/2026 | Approved | RYAN SALAZAR |
| Underground Mechanical | 4/9/2026 | Corrections Issued | WILBER ROSALES |
| Underground Mechanical | 4/14/2026 | Approved | WILBER ROSALES |
| ELECTRICAL-Final | 4/21/2026 | Approved | EVAN COOPER |
| Final | 4/21/2026 | Permit Finaled | EVAN COOPER |
| HVAC-Final | 4/21/2026 | Approved | EVAN COOPER |
| PLUMBING-Final | 4/21/2026 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 4/21/2026 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 4/21/2026 | Approved | EVAN COOPER |