13575 1/2 W DYER ST 91342

Certificate Information: 13575 1/2 W DYER ST 91342

Application / Permit
25016-10000-10987
Plan Check / Job No.
B25VN06425
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN. Conversion of detached garage to detached ADU per LAMC 12.22A.33(b)(1)
Permit Issued
Issued on 5/6/2025
Issuing Office
Current Status
CofO Issued on 10/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/10/2025 APPLICANT
Assigned to Plan Check Engineer 3/27/2025 JESSE VIDUYA
Corrections Issued 4/9/2025 JESSE VIDUYA
Quality Review Completed 4/17/2025 CHAD DOI
Applicant returned to address corrections 4/25/2025 JESSE VIDUYA
Plan Check Approved 5/6/2025 JESSE VIDUYA
Issued 5/6/2025 APPLICANT
CofO in Progress 10/6/2025 KEVIN BERBERYAN
CofO Issued 10/14/2025 RUBEN SALAS
Permit Finaled 10/14/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/25/2025 COLIN LOREDO
Eng Process Fee Ord 176,300 Cleared 4/25/2025 COLIN LOREDO
Sewer availability Cleared 4/25/2025 COLIN LOREDO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/27/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 9/8/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 9/8/2025 Approved MICHEL ABAJAN
Green Building Rough 9/8/2025 Approved MICHEL ABAJAN
HVAC-Rough 9/8/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 9/8/2025 Approved MICHEL ABAJAN
Insulation 9/10/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 9/10/2025 Approved KEVIN BERBERYAN
Drywall Nailing 9/15/2025 Approved KEVIN BERBERYAN
PLUMBING-Rough 9/15/2025 Approved KEVIN BERBERYAN
Pre-Inspection 9/17/2025 Partial Inspection KEVIN BERBERYAN
HVAC-Final 9/25/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 9/30/2025 Approved KEVIN BERBERYAN
Final 9/30/2025 Corrections Issued KEVIN BERBERYAN
Green Building Final 9/30/2025 Not Ready for Inspection KEVIN BERBERYAN
HVAC-Final 9/30/2025 Approved KEVIN BERBERYAN
PLUMBING-Final 9/30/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 9/30/2025 SGSOV Approved KEVIN BERBERYAN
Smoke Detectors 9/30/2025 Approved KEVIN BERBERYAN
Final 10/6/2025 OK to Issue CofO KEVIN BERBERYAN
Green Building Final 10/6/2025 Approved KEVIN BERBERYAN