13575 1/2 W DYER ST 91342
Certificate Information: 13575 1/2 W DYER ST 91342
- Application / Permit
- 25016-10000-10987
- Plan Check / Job No.
- B25VN06425
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. Conversion of detached garage to detached ADU per LAMC 12.22A.33(b)(1)
- Permit Issued
- Issued on 5/6/2025
- Issuing Office
- Current Status
- CofO Issued on 10/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 3/27/2025 | JESSE VIDUYA |
| Corrections Issued | 4/9/2025 | JESSE VIDUYA |
| Quality Review Completed | 4/17/2025 | CHAD DOI |
| Applicant returned to address corrections | 4/25/2025 | JESSE VIDUYA |
| Plan Check Approved | 5/6/2025 | JESSE VIDUYA |
| Issued | 5/6/2025 | APPLICANT |
| CofO in Progress | 10/6/2025 | KEVIN BERBERYAN |
| CofO Issued | 10/14/2025 | RUBEN SALAS |
| Permit Finaled | 10/14/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2025 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2025 | COLIN LOREDO |
| Sewer availability | Cleared | 4/25/2025 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/27/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/8/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 9/8/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 9/8/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 9/8/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 9/8/2025 | Approved | MICHEL ABAJAN |
| Insulation | 9/10/2025 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/10/2025 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 9/15/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/15/2025 | Approved | KEVIN BERBERYAN |
| Pre-Inspection | 9/17/2025 | Partial Inspection | KEVIN BERBERYAN |
| HVAC-Final | 9/25/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 9/30/2025 | Approved | KEVIN BERBERYAN |
| Final | 9/30/2025 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 9/30/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 9/30/2025 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 9/30/2025 | Approved | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 9/30/2025 | SGSOV Approved | KEVIN BERBERYAN |
| Smoke Detectors | 9/30/2025 | Approved | KEVIN BERBERYAN |
| Final | 10/6/2025 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 10/6/2025 | Approved | KEVIN BERBERYAN |