3345 N PRIMERA AVE 90068
Certificate Information: 3345 N PRIMERA AVE 90068
- Application / Permit
- 25016-10000-10894
- Plan Check / Job No.
- B25LA13805
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan. Convert 400 ft of detached garage into an detached Accessory Dwelling Unit (ADU) .
- Permit Issued
- Issued on 4/24/2025
- Issuing Office
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2025 | ADAM HEGAZI |
| Corrections Issued | 4/15/2025 | ADAM HEGAZI |
| Plan Check Approved | 4/22/2025 | TSE MING HUANG |
| Issued | 4/24/2025 | APPLICANT |
| CofO in Progress | 11/4/2025 | BRIAN SULLIVAN |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/18/2025 | RYAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 4/18/2025 | RYAN CASTRO |
| Sewer availability | Cleared | 4/18/2025 | RYAN CASTRO |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Fire And Casualty Company; Lic. No.: 990126-B | , |
| Contractor | Four Seasons Builders Inc; Lic. No.: 990126-B | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/4/2025 | Conditional Approval | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/5/2025 | Approved | BRIAN SULLIVAN |
| Wood Frame | 6/17/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2025 | Partial Approval | BRIAN SULLIVAN |
| Rough-Elec/Plmb/HVAC | 7/10/2025 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 7/17/2025 | Approved | ROY SPAULDING |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2025 | Approved | ROY SPAULDING |
| Gas Test | 7/17/2025 | Partial Approval | ROY SPAULDING |
| HVAC-Rough | 7/17/2025 | Approved | ROY SPAULDING |
| PLUMBING-Rough | 7/17/2025 | Approved | ROY SPAULDING |
| Rough-Elec/Plmb/HVAC | 7/17/2025 | Approved | ROY SPAULDING |
| Sewer | 7/17/2025 | Not Ready for Inspection | ROY SPAULDING |
| Gas Test | 7/21/2025 | Approved | ROY SPAULDING |
| Insulation | 7/21/2025 | Approved | ROY SPAULDING |
| Sewer | 7/21/2025 | Approved | ROY SPAULDING |
| Interior/Exterior Lathing | 8/8/2025 | Partial Approval | BRIAN SULLIVAN |
| Shower Pan | 8/8/2025 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 8/12/2025 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 8/19/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 10/15/2025 | Approved | DAVID WILLIAMS |
| Final | 10/15/2025 | Corrections Issued | DAVID WILLIAMS |
| Green Building Final | 10/15/2025 | Approved | DAVID WILLIAMS |
| HVAC-Final | 10/15/2025 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 10/15/2025 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 10/15/2025 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 10/15/2025 | Approved | DAVID WILLIAMS |
| ELECTRICAL-Final | 10/24/2025 | Partial Inspection | BRIAN SULLIVAN |
| Final | 10/24/2025 | Corrections Issued | BRIAN SULLIVAN |
| HVAC-Final | 10/24/2025 | Partial Inspection | BRIAN SULLIVAN |
| PLUMBING-Final | 10/24/2025 | Partial Inspection | BRIAN SULLIVAN |
| Final | 11/3/2025 | OK to Issue CofO | BRIAN SULLIVAN |