10700 W TABOR ST SUITE 102 90034
Certificate Information: 10700 W TABOR ST SUITE 102 90034
- Application / Permit
- 25016-10000-10868
- Plan Check / Job No.
- B25LA13788
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- EPLAN: CHANGE OF USE FROM RETAIL STORE TO (N) RESTAURANT
- Permit Issued
- Issued on 10/13/2025
- Issuing Office
- Current Status
- CofO Issued on 5/8/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/14/2025 | GURUNATH NESARAJAH |
| Corrections Issued | 4/15/2025 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 4/22/2025 | GURUNATH NESARAJAH |
| Plan Check Approved | 7/23/2025 | PINANK PATEL |
| Issued | 10/13/2025 | APPLICANT |
| CofO in Progress | 5/7/2026 | FARHAD DADBIN |
| CofO in Progress | 5/7/2026 | DOUGLAS KENNEDY |
| Permit Finaled | 5/8/2026 | VASIL MIHALEV |
| CofO Issued | 5/8/2026 | VASIL MIHALEV |
| Permit Finaled | 5/8/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| Miscellaneous | Cleared | 4/17/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 4/17/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 4/17/2025 | JACQUELINE TORRES |
| Specific Plan | Cleared | 4/17/2025 | KYLE WINSTON |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2025 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 5/2/2025 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 5/7/2025 | JOSHUA JONES |
| Food Service Establishment | Cleared | 7/21/2025 | STANLEY WING |
| Food establishment approval | Cleared | 7/25/2025 | LACDHS APPROVED |
| Miscellaneous | Cleared | 8/26/2025 | JACQUELINE TORRES |
Contact Information
| Contractor | Tripalink Builders Llc; Lic. No.: 1118224-B | , |
Inspector Information
| FARHAD DADBIN, (310) 914-3922 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 12/17/2025 | Not Ready for Inspection | FARHAD DADBIN |
| Pre-Inspection | 12/17/2025 | Approved | FARHAD DADBIN |
| Wood Frame | 1/27/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Light Gage Steel Frame | 1/30/2026 | Partial Approval | FARHAD DADBIN |
| Final | 3/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Reinforced Concrete Frame | 3/18/2026 | Approved | FARHAD DADBIN |
| SGSOV-Seismic Gas S/O Valve | 3/18/2026 | SGSOV Approved | FARHAD DADBIN |
| Smoke Detectors | 3/18/2026 | Not Ready for Inspection | FARHAD DADBIN |
| Final | 5/6/2026 | OK to Issue CofO | FARHAD DADBIN |
| Smoke Detectors | 5/6/2026 | Approved | FARHAD DADBIN |