4443 E YELLOWSTONE ST 90032
Certificate Information: 4443 E YELLOWSTONE ST 90032
- Application / Permit
- 25016-10000-10840
- Plan Check / Job No.
- B25LA13748
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE TO NEW DETACHED ACCESORY DWELLING UNIT PER PER GC 66323(a)(1)
- Permit Issued
- Issued on 7/5/2025
- Issuing Office
- Current Status
- CofO Issued on 2/10/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/11/2025 | MIROOSH KHACHATOORIAN |
| Corrections Issued | 4/14/2025 | MIROOSH KHACHATOORIAN |
| Plan Check Approved | 7/3/2025 | MIROOSH KHACHATOORIAN |
| Issued | 7/5/2025 | APPLICANT |
| CofO in Progress | 2/9/2026 | LILIANA PORTILLO |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
| CofO Issued | 2/10/2026 | DEROLD HAUFF |
| Permit Finaled | 2/10/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| "Q" conditions | Cleared | 4/14/2025 | JASON CHAN |
| Address approval | Cleared | 4/14/2025 | JESSICA OPINION |
| Roof/Waste drainage to street | Cleared | 4/14/2025 | JESSICA OPINION |
| Sewer availability | Cleared | 4/14/2025 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 4/16/2025 | RYAN CASTRO |
| Grading Pre-Inspection | Cleared | 4/17/2025 | MICHAEL TEMPLE |
| Construction near power lines | Cleared | 6/26/2025 | RIDWAN HARDY |
| Construction within easement | Cleared | 6/26/2025 | RIDWAN HARDY |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: C30383 | 5739 KANAN ROAD # 133 AGOURA HILLS, CA 91301 |
| Contractor | L E A D Enterprises Inc; Lic. No.: 955824-B | , |
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/24/2025 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 7/24/2025 | Partial Approval | BRENDAN MORELLI |
| Underground Mechanical | 8/5/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/19/2025 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 9/19/2025 | Approved | LILIANA PORTILLO |
| Gas Test | 9/19/2025 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 9/19/2025 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 9/19/2025 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/2/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Interior/Exterior Lathing | 10/2/2025 | Partial Approval | LILIANA PORTILLO |
| Insulation | 10/6/2025 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 10/16/2025 | Approved | REGINA MENDEZ |
| Insulation | 10/16/2025 | Approved | REGINA MENDEZ |
| Interior/Exterior Lathing | 10/22/2025 | Approved | REGINA MENDEZ |
| Shower Pan | 10/22/2025 | Approved | REGINA MENDEZ |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/4/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 12/4/2025 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 12/4/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 12/4/2025 | Approved | LILIANA PORTILLO |
| HVAC-Final | 12/4/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Final | 12/4/2025 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 12/4/2025 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| Green Building Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| HVAC-Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| PLUMBING-Final | 12/30/2025 | Not Ready for Inspection | JOSH MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/30/2025 | SGSOV Not Ready | JOSH MEISTER |
| ELECTRICAL-Final | 1/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/7/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Final | 1/7/2026 | Approved | LILIANA PORTILLO |
| HVAC-Final | 1/7/2026 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/7/2026 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/7/2026 | SGSOV Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/4/2026 | Corrections Issued | LILIANA PORTILLO |
| Final | 2/4/2026 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 2/6/2026 | Approved | LILIANA PORTILLO |
| Final | 2/6/2026 | OK to Issue CofO | LILIANA PORTILLO |