1269 W 35TH ST 90007
Certificate Information: 1269 W 35TH ST 90007
- Application / Permit
- 25016-10000-10614
- Plan Check / Job No.
- B25LA13495
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert (E) Detached Accessory Structure [Garage (241 SF) and Recreation Room (333 SF)] and unpermitted portion (49 SF) constructed before January 1, 2020 to Accessory Dwelling Unit (623 SF) with covered entry (41 SF) per AB 2533, & CA Govt Code Section 66314-66332, & 66333-66339 .
- Permit Issued
- Issued on 12/4/2025
- Issuing Office
- Current Status
- Issued on 12/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/10/2025 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2025 | GEORGE ALVAREZ |
| Corrections Issued | 4/16/2025 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 11/19/2025 | EDWIN MARTINEZ |
| Plan Check Approved | 12/4/2025 | GEORGE ALVAREZ |
| Issued | 12/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2025 | ADRIAN SANCHEZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/1/2025 | ADRIAN SANCHEZ |
| Roof/Waste drainage to street | Cleared | 5/1/2025 | ADRIAN SANCHEZ |
| Sewer availability | Cleared | 5/1/2025 | ADRIAN SANCHEZ |
| Community Plan Implem. Overlay | Cleared | 5/27/2025 | MANERI ROMAN |
| City Hist. Cultural Monument | Cleared | 10/31/2025 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 10/31/2025 | LAMBERT GIESSINGER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 12/10/2025 | Corrections Issued | SABAS ALONSO |
| Deputy Wood Construction | 12/23/2025 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 12/29/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/26/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2026 | Partial Approval | SABAS ALONSO |
| Sewer | 3/26/2026 | Approved | SABAS ALONSO |
| Underground Mechanical | 3/26/2026 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2026 | Corrections Issued | SABAS ALONSO |
| METHANE-Rough | 4/3/2026 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/23/2026 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 4/23/2026 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 4/29/2026 | Approved | SABAS ALONSO |
| Green Building Rough | 4/29/2026 | Approved | SABAS ALONSO |
| HVAC-Rough | 4/29/2026 | Approved | SABAS ALONSO |
| Interior/Exterior Lathing | 4/29/2026 | Partial Approval | SABAS ALONSO |
| Insulation | 5/19/2026 | Approved | ALEX COLIN |
| Drywall Nailing | 5/26/2026 | Approved | LILIANA PORTILLO |