2634 S MANHATTAN PL 90018
Certificate Information: 2634 S MANHATTAN PL 90018
- Application / Permit
- 25016-10000-10403
- Plan Check / Job No.
- X25LA13256
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Re-roof with Class A or B material weighing less than 6 pounds per sq. ft. over NEWsolid sheathing ___42___Squares. Class A roof covering is required within Very High Fire Hazard Severity Zone (VHFHSZ). Forresidential roof replacement > 50% of the total roof area, apply Cool Roof Product labeled and certified by CoolRoof Rating Council (CRRC). Cool Roof may be required for non-residential buildings per Title 24, Part 6, Section 141(b) 2B.
- Permit Issued
- Issued on 4/21/2025
- Issuing Office
- Current Status
- Issued on 4/21/2025
Permit Application Status History
| No Progress | 4/4/2025 | JACKELINE RUIZ |
| Issued | 4/21/2025 | APPLICANT |
Permit Application Clearance Information
| HPOZ | Cleared | 4/8/2025 | DANIEL MATA |
Contact Information
| Contractor | Citiwide Builders Inc; Lic. No.: 1064959-B | 140 E LEMON AVE MONROVIA, CA 91016 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 5/5/2025 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 5/5/2025 | SGSOV Not Required | ALFREDO LOPEZ |
| Smoke Detectors | 5/5/2025 | Partial Inspection | ALFREDO LOPEZ |